Commercial Electrical, Elevator, Hvac/Mechanical, Roofing work permitted December 9, 2024, with 12 permits through October 2, 2026, declaring $1,402,236 of work. Contractor on record: Otis Elevator Company.
Replace (2) water cooled chillers, (2) chilled water pumps, and (2) condenser water pumps.
Seattle permit records name Otis Elevator Company, 16d LLC and Holaday Parks Inc as the contractors on this project, among 5 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
12 permits issued Dec 9 – Oct 2, newest first.
| Issued | Permit | Contractor | Value |
|---|
Commercial and multifamily, biggest first.
#7165522-EL Electrical · Electrical 43118 PERFORM GENERATOR LOAD BANK Status: Issued | Not published | — |
| applied Jul 7 | #7151198-CY Conveyance · Trade Residence Inn SLU - ELV 3 - MOD: NEW; Gearless machine, controller, hall and car fixtures, governor, 2way emergency comms. EQP-SI-06157 / EQP-CY-04283 (2021 SBC = 2023 NEC/SEC = 2019 A17.1 = 2020 A18.1) Status: Issued | Otis Elevator Company | $216K |
| applied Apr 6 | #7136792-CY Conveyance · Trade Residence Inn SLU - ELV 4 - MOD: NEW; Gearless machine, controller, hall and car fixtures, governor, 2way emergency comms. EQP-SI-06157 / EQP-CY-04284 (2021 SBC = 2019 A17.1 = 2023 NEC/SEC = 2020 A18.1) Status: Issued | Otis Elevator Company | $216K |
| applied Dec 10 | #7114295-ME Mechanical · Trade Replace (2) water cooled chillers, (2) chilled water pumps, and (2) condenser water pumps. Status: Issued | Not published | $737K |
| applied Feb 17 | #7129560-EL Electrical · Electrical Replace elevator disconnects using existing feeders and upstream OCP. Upsize machine room panel to accommodate elevator utilization circuits OCP. Upgrade mach room and pit lighting to LED. Status: Completed | 16d LLC | $18.2K |
#7130736-EL Electrical · Electrical Adding altering (7) circuits for chillers, VFDs, and EF. Low voltage connections for 1 controller and (7) devices. Whole building. Status: Completed | Holaday Parks Inc | — |
#7129614-EL Electrical · Electrical For the purpose of elevator modernization: Install hat relays in existing elevator machine rooms Status: Issued | 16d LLC | — |
| applied Jan 14 | #7124920-CY Conveyance · Trade Residence Inn SLU - ELV 1 - Hydro MOD: NEW: Controller, Power Unit, Fixtures, Door Operator, Door Protection, 2Way Em Comms EQP-SI-06157 / EQP-CY-04286 (2021 SBC = 2019 A17.1 = 2023 NEC/SEC = 2020 A18.1) Status: Issued | Otis Elevator Company | $216K |
| applied Jan 14 | #7124929-CY Conveyance · Trade Residence Inn SLU - ELV 2 - Hydro MOD- NEW Controller, Power Unit, Fixtures, Door Operator, Door Protection, 2way em comms EQP-SI-06157 / EQP-CY-04285 (2021 SBC = 2019 A17.1 = 2023 NEC/SEC = 2020 A18.1) Status: Issued | Otis Elevator Company | $216K |
#7111252-EL Electrical · Electrical 41002 PERFORM GENERATOR LOAD BANK ON STANDBY Status: Completed | Not published | $500 |
#7088675-RR Roof · Roof Install 1/4" primed Dens Deck over existing single roof system Dens Deck will be adhered to roof surface using low rise foam insulation. Adhere 60 mill TPO on top of the Dens Deck using bonding adhesive. New metal edge detail. System includes a 20 year labor and material warranty Status: Completed | Centimark | $362K |
| applied Nov 1 | #7054081-EL Electrical · Electrical Modify existing fire alarm system for tenant improvements. Decommission existing fire alarm control panel, replace with (1) new Simplex 4100ES Panel. Marriott Residence Inn Lake Union. 800 Fairview Ave North Seattle, WA 98109. Status: Completed | Johnson Controls Fire Protection | $69K |