Get ProEvery project in every city · from $33/mo
Get Promultifamily project · Seattle, WA
Multifamily General Building, Demolition, Electrical, Elevator, Fire Protection, Hvac/Mechanical work permitted February 18, 2025, with 22 permits through September 28, 2026, declaring $38,259,175 of work. Contractor on record: Trademark Plumbing.
Demolish existing mixed-use structure per plan.
Seattle permit records name Trademark Plumbing, Otis Elevator Company and Kirby Electric Incorporated as the contractors on this project, among 8 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
22 permits issued Feb 18 – Sep 28, newest first.
Commercial and multifamily, biggest first.
| Issued | Permit | Contractor | Value |
|---|
| applied Sep 28 | #7164329-RF Refrigeration · Trade Refer permit for Dog Wash Mini Split Status: Issued | Pacific One Construction Inc | $1.5K |
| applied Sep 15 | #7162557-CY Conveyance · Trade Temp Use - Car#1 7127785-CY (Original Installation Permit) 60 day temporary use permit valid from date signed by City of Seattle Elevator Inspector. Must have two way communication with operator at all times. Status: Completed | Otis Elevator | $500 |
| applied Jul 24 | #7147882-CN Addition/Alteration · Building Construct initial tenant improvement in street level space for a canine grooming facility occupy per plans Status: Issued | Not published | $90K |
#7157451-BP Boiler/Pressure Vessel · Trade New 6 story apartment building Status: Issued | Trademark Plumbing | $2M | |
#7157444-BP Boiler/Pressure Vessel · Trade 6 Story Apartment Building. Status: Issued | Trademark Plumbing | $2M | |
#7157454-BP Boiler/Pressure Vessel · Trade New 6 Story Apartment Building Status: Issued | Trademark Plumbing | $2M | |
#7157445-BP Boiler/Pressure Vessel · Trade 6 Story Apartment Building Status: Issued | Trademark Plumbing | $2M | |
#7157449-BP Boiler/Pressure Vessel · Trade 6 Story Apartment Building Status: Issued | Trademark Plumbing | $2M | |
| applied May 6 | #7141838-FS Fire Sprinkler and Suppression · Trade Install Captive Aire TANK System into Kitchen Hood Status: Issued | Vulnix Fire Protection | $1K |
| applied Mar 19 | #7134046-EL Electrical · Electrical This is a post-permit revision for permit #7092779-EL. Status: Issued | Northwest Fire Systems LLC | $24.9K |
| applied Mar 9 | #7132467-RF Refrigeration · Trade Heat Pumps for new apartments building Status: Issued | Pacific One Construction Inc | $5K |
| applied Jan 28 | #7126913-FS Fire Sprinkler and Suppression · Trade NEW CONSTRUCTION, FULL 13 SYSTEM, WET AND DRY SYSTEMS, 2 CLASS I STANDPIPES AND 748 SPRINKLER HEADS Status: Issued | Not published | $197K |
| applied Jan 21 | #7112070-CN Addition/Alteration · Building Establish use as restaurant per land use code. Construct initial tenant improvements in mixed use building on SE corner of ground floor (Drip Drip Coffee) per plan. Status: Issued | Not published | $175K |
| applied Feb 5 | #7127786-CY Conveyance · Trade Installation of gen3 Edge traction Elevator - N1JX43 6804313-CN (Construction Permit) 2018 SBC = 2020 SEC = 2019 A17.1 = 2017 A18.1 Status: Issued | Otis Elevator Company | $173K |
| applied Feb 5 | #7127785-CY Conveyance · Trade Installation of Gen3 Edge Traction Elevator - N1JX42 6804313-CN (Construction Permit) 2018 SBC = 2020 SEC = 2019 A17.1 = 2017 A18.1 Status: Issued | Otis Elevator Company | $194K |
#7126453-EL Electrical · Electrical Low voltage install of ERCES/DAS in 6 Level Building (plus roof). 4 in-building antennas per floor. Headend unit is located Level 1 Rm 102 (next to the electrical room). Status: Completed | Clearline Engineering | — | |
#7117217-EL Electrical · Electrical Electrical TI that will utilize the existing service from the building for said space. Including adding (2) disconnects, receptacles, lighting, electrical low voltage wiring, and equipment connections. Status: Issued | Kirby Electric Incorporated | $53.9K | |
| applied Jun 24 | #7092779-EL Electrical · Electrical Installing a new fire alarm system with notification, elevator recall and pressurization controls, and sprinkler monitoring. 9/21/2026 jnl renewal Status: Issued | Northwest Fire Systems | $173K |
| applied Jan 8 | #7063965-EL Electrical · Electrical Furnish and install design build electrical system including installing a 4000A service, panels, transformer, disconnects, lighting, phone/ data, CATV, CCTV, and Access Control. [5/6/25 BGO - Approved Plan Set] **Renewed per Zendesk, EC, 4/8/26** Status: Issued | Kirby Electric Incorporated | $1.8M |
| applied Jul 14 | #6804313-CN New · Building Construct new mixed use building occupy per plan. Mechanical included. Status: Issued | Rush Construction | $13.4M |
| applied Jan 10 | #7063741-DM Demolition · Demolition Demolish existing mixed-use structure per plan. Status: Completed | Not published | $20M |
| applied Jan 14 | #7065180-EL Electrical · Electrical 800A Temp Power. [2/18/25 KEF - Plan set approved] [1-21-26 D Rankin - Permit extended for one year] Status: Issued | Kirby Electric Incorporated | $16.4K |