Get ProEvery project in every city · from $79/mo
Get Procommercial project · Seattle, WA
Commercial General Building, Electrical, Elevator, Fire Protection, Hvac/Mechanical work permitted May 23, 2025, with 17 permits through October 19, 2026, declaring $1,766,860 of work. Contractor on record: UMC, Inc..
Construct interior alterations to existing single family residence. per STFI
Seattle permit records name UMC, Inc., Evergreen Power Systems, Inc and Otis Elevator Company as the contractors on this project, among 6 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
The contractor on 2 permits issued in the last 30 days is included with Pro.
See the contractorCommercial and multifamily, biggest first.
17 permits issued May 23 – Oct 19, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Oct 19 | #7168084-RF Refrigeration · Trade Install a new 1-ton split-system AC unit to serve existing Elevator Machine Room. Status: Issued | Contractor with Pro | $10.7K |
#7166141-EL Electrical · Electrical Modernization of elevator and mechanical room. Replace disconnect and connections to elevator controller. Add vapor tight lights in mechanical room and pit. Add power for Mini split. Add sub panel in mech room. Adjust circuits in mechanical room to new sub panel. Replace receptacles with GFCI. Status: Issued | Contractor with Pro | — | |
#7159861-EL Electrical · Electrical 42539 PERFORM GENERATOR LOAD BANK Status: Completed | Not published | — | |
#7159866-EL Electrical · Electrical 42540 PERFORM GENERATOR LOAD BANK Status: Completed | Not published | — | |
| applied Jun 10 | #7139866-CN Addition/Alteration · Building Construct interior alterations to Institutional Nursing Home (Kline Galland Home) at levels 2-3 per plan. Status: Completed | Not published | $350K |
| applied May 21 | #7114130-ME Mechanical · Trade Remove and replace existing rooftop unit(s), per plan Status: Issued | Not published | $247K |
#7138390-EL Electrical · Electrical 21203 - KGH - Add/alter lighting, outlets, switches. Status: Completed | Evergreen Power Systems, Inc | — | |
| applied Apr 14 | #7133515-CY Conveyance · Trade Pump unit, controller, fixtures, COP, two-way communication, tape reader, interlocks, door hardware - Elev. B EQP-SI-05436 / EQP-CY-02833 (2021 SBC = 2019 A17.1 = 2023 NEC/SEC = 2020 A18.1) Status: Issued | Otis Elevator Company | $120K |
| applied Mar 5 | #7131924-RF Refrigeration · Trade The existing LG VRF Systems are using R410a refrigerant. This refrigerant, R410a, and the parts for this LG equipment will be phased out starting this year, causing repair costs to increase and parts less available. RECOMMENDATIONS The current systems, #4 and #20 are at the end of their useful… Status: Issued | UMC, Inc. | $268K |
| applied Jan 15 | #7125135-CY Conveyance · Trade Jack replacement EQP-SI-05436 / EQP-CY-02833 (2021 SBC = 2019 A17.1 = 2023 NEC/SEC = 2020 A18.1) Status: Completed | Artline | $103K |
| applied Oct 30 | #7114407-RF Refrigeration · Trade Kline Galland Home is being proactive in replacement of aging LG VRF systems. The last system replacement (#10) was replaced in March of 2024. CURRENT SYSTEM DESCRIPTION The LG VRF Systems are using R410a refrigerant. This refrigerant, R410a, and the parts for this LG equipment will be phased out… Status: Completed | UMC, Inc. | $247K |
#7110836-FS Fire Sprinkler and Suppression · Trade lowering 4 pendents for new ceilings Status: Completed | Not published | $9K | |
#7105745-EL Electrical · Electrical Kline Galland Seward Park - Job 1022038: Life Skills Power: Provide and install (3) GFCI duplex outlets and (10) duplex outelts and plates only. Life Skills Lighting: Demo (8) 2x2 light fixtures. Provide and install (9) 2x2 LED fixtures and (11) recessed down lights Provide and instal (1) Under… Status: Completed | Prime Electric | $33.1K | |
#7103531-EL Electrical · Electrical PERFORM GENERATOR LOAD BANK Status: Completed | Not published | $500 | |
#7103539-EL Electrical · Electrical perform generator load bank Status: Completed | Not published | $500 | |
#7103543-EL Electrical · Electrical Installing 8500ft of CAT5e cable for cameras. Cable will terminate at 2 24 port patch panels. Status: Completed | Interface Technologies Northwest | $3.5K | |
| applied May 13 | #7085676-CN Addition/Alteration · Building Construct interior alterations to existing single family residence. per STFI Status: Completed | Not published | $375K |
In Seattle, biggest first.