Commercial General Building, Electrical, Elevator, Fire Protection, Hvac/Mechanical work permitted November 22, 2024, with 40 permits through October 9, 2026, declaring $11,993,333 of work. Contractor on record: 16d LLC.
The electrical project scope includes providing feeders in concrete encased ductbanks between electrical equipment provided by a third party. All details of the electrical equipment, including overcurrent protection, are proprietary. The electrical equipment design is provided at the end of the uploaded plan set. 15kV feeders and 600V and below communications cabling are being routed between new transformers and switchgear in the equipment yard. These feeders are extended from the switch
Seattle permit records name 16d LLC, McKinstry Co LLC and EC Electric as the contractors on this project, among 18 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
Commercial and multifamily, biggest first.
40 permits issued Nov 22 – Oct 9, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
#7166774-EL Electrical · Electrical Building A: New Building Power Meter Building B: New Building Power Meter, Solar Power Meter, External floodlight Job 81980 Status: Issued | Contractor with Pro | — | |
| applied Oct 7 | #7157977-ME Mechanical · Trade Install split unit in existing elevator machine room STFI (Subject to Field Inspection) Status: Completed | Not published | $7.9K |
#7166138-EL Electrical · Electrical Underground pathway for future EV chagers and electrical equipment. Status: Issued | Contractor with Pro | — | |
| applied Jun 5 | #7135174-CN Addition/Alteration · Building Construct utility improvements including new transformer vaults at Terminal 91 - Port of Seattle per plan. Status: Issued | Not published | $400K |
#7160753-EL Electrical · Electrical Installation of AES radio Status: Completed | Guardian Security Systems Inc | — | |
#7160755-EL Electrical · Electrical Installation of AES radio Status: Completed | Guardian Security Systems Inc | — | |
| applied Jul 30 | #7155631-GR Grading · Grading Construct excavation and grading for terminal 91 for Port of Seattle per plan. Status: Issued | Not published | $50K |
#7158219-EL Electrical · Electrical We are the HVAC contractor for the modular buildings A & B being installed at Terminal 91. We are installing new VRV systems at each building. Building A has 13 controllers / thermostats, and Building B has 26. Status: Completed | Harris Pacific Northwest LLC | — | |
| applied Aug 13 | #7157982-RF Refrigeration · Trade For the purpose of elevator modernization: Refrigeration permit for 7157977-ME Status: Completed | 16d LLC | $7.9K |
| applied Jul 27 | #7155069-EL Electrical · Electrical The electrical project scope includes providing feeders in concrete encased ductbanks between electrical equipment provided by a third party. All details of the electrical equipment, including overcurrent protection, are proprietary. The electrical equipment design is provided at the end of the… Status: Issued | VECA Electric Comapny | $6M |
#7154872-EL Electrical · Electrical Building A: Circuit for new Fire Alarm Panel, Circuit for 30A twist lock receptacle, 4x building interconnections Building B: Circuit for new Fire Alarm Panel, Circuit for 30A twist lock receptacle, 200A feeder for sub panel, additional quad plex receptacle, 12 x building interconnections Job #81980 Status: Issued | EC Electric | — | |
#7153955-EL Electrical · Electrical @ LINEAGE LOGISTICS II ELECTRICAL FOR ELEVATOR MODERNIZATION Status: Completed | 16d LLC | — | |
#7153691-EL Electrical · Electrical Load bank testing on back up electric generator - SR00126673 Status: Issued | Pacific Power Group | — | |
#7152614-EL Electrical · Electrical Bldg A - Comroom build out. Adding low voltage outlets. Status: Completed | Precision Electric Group, Inc | — | |
#7152617-EL Electrical · Electrical Bldg B - ComRoom Build Out. Installing data outlets, installing access control panel and card readers. Status: Completed | Precision Electric Group, Inc | — | |
#7151528-EL Electrical · Electrical Adding a dedicated circuit for heat trace Status: Completed | Luquette Electrical Group, Inc. | — | |
#7149154-EL Electrical · Electrical Installing cat6 cables for data and intercom locations. PowerCom job# 451813 Status: Completed | PowerCom, Inc. | — | |
| applied Jun 23 | #7092535-FS Fire Sprinkler and Suppression · Trade New sprinkler system for new modular building construction Status: Completed | Emerald Fire | $33K |
| applied Aug 27 | #7021243-CN New · Building Install south Modular Building A occupy per plan. (Construct site improvements and foundation work to install (2) modular buildings at pier 90 per plan. Review & process for (2) records under 7021243-CN) Status: Completed | Not published | $121K |
| applied Aug 27 | #7103941-CN New · Building Install north Modular Building B occupy per plan (Construct site improvements and foundation work to install (2) modular buildings at pier 90 per plan. Review & process for (2) records under 7021243-CN) Status: Completed | Not published | $262K |
#7131702-EL Electrical · Electrical CFL to LED to reduce load. Status: Issued | Lumenal Lighting, LLC. | — | |
#7126855-EL Electrical · Electrical Status: Completed | Apex Electrical Group LLC | — | |
| applied Nov 10 | #7115786-EL Electrical · Electrical Modify existing fire alarm system. Installation of (97) new fire alarm devices and (3) new panels. This includes new manual pull stations, photoelectric smoke sensors, CO sensor bases, horn/strobes, strobes, supervised IAMs, surge protection devices, and batteries. System components are compatible… Status: Issued | Johnson Controls Fire Protection | $80K |
#7118934-BP Boiler/Pressure Vessel · Trade Installation of one compressor package, including two ASME-rated pressure vessels. National Board #30661-30665 Serial # 316959 Status: Completed | McKinstry Co LLC | $181K | |
#7118935-BP Boiler/Pressure Vessel · Trade Installation of one compressor package, including two ASME-rated pressure vessels. National Board # 30661-30665 Status: Completed | McKinstry Co LLC | $181K | |
| applied Jul 10 | #7029969-CN New · Building Install 2 pre-manufactured buildings on an industrial site per plan. Status: Issued | Not published | $165K |
| applied Jan 21 | #7065791-EL Electrical · Electrical Terminal 91 berth 6 and 8 Status: Completed | EC Electric | $3.3M |
| applied Apr 11 | #7012638-GR Grading · Grading Construct sitework for Port of Seattle per plan [no retaining walls permitted] Status: Issued | Not published | $863K |
| applied Feb 19 | #7071354-EL Electrical · Electrical Installation of rooftop Solar Photovoltaic System Consisting of 40.12kW - (68) QCells Q.PEAK DUO XL-G11 590. (2) SolarEdge SE17.3K-US. [4/17/25 BGO - Approved PV Plan Set] [3/18/26 BGO - Permit Extended One Year] Status: Completed | Puget Sound Solar | $100K |
| applied Mar 5 | #7073072-EL Electrical · Electrical Lineage Logistics-114032910-Revision to permit 6900778-EL Revisions are indicated with pink bubbling on submitted plans to show changes. 3/20/2026 renewal.[10/16/2026 JBC Note this fire alarm is in building 390, 391 & 392] Status: Issued | Not published | $3.3K |
#7075898-EL Electrical · Electrical INSTALLING (4) 125AMP/3POLE 480V CIRCUIT BREAKERS AND (4) DISCONNECT SWITCHES TO POWER FUTURE RECEPTACLES. (RECEPTACLES TO BE INSTALLED BY OTHERS) Status: Completed | Clinton and Sons Electric Inc | $25K | |
#7072531-EL Electrical · Electrical #19405 T91 CRUISE LINE FA - disconnect and reconnect (4) NAC Panels. disconnect and reconnect (1) Fire Panel Status: Completed | Evergreen Power Systems, Inc | $2K | |
#7071117-EL Electrical · Electrical Re-route (3) feeder conduits overhead in warehouse space Status: Completed | EC Electric | $85K | |
| applied Jan 28 | #7062529-ME Mechanical · Trade Install split unit in existing elevator machine room and nearby outdoor planter area per plans Status: Completed | Not published | $9.4K |
#7067159-EL Electrical · Electrical INSTALL1-1/4" AND 2" TELECOM/FIBER PATHWAY (CONDUITS ONLY) INSTALL (3) JUNCTION BOXES AT GANGWAY LOCATIONS FOR FIBER TERMINATIONS (J-BOX AND CONDUITS ONLY) Status: Completed | Clinton and Sons Electric Inc | $25K | |
#7063367-BP Boiler/Pressure Vessel · Trade Compressor replacement. National Board # 30075-30079 Serial # C430162A Status: Completed | McKinstry Co LLC | $155K | |
#7063371-BP Boiler/Pressure Vessel · Trade Compressor Replacement. National Board # 10588 Serial # 24-056. Status: Completed | McKinstry Co LLC | $155K | |
| applied Dec 26 | #7062531-RF Refrigeration · Trade For the purpose of elevator modernization: mechanical permit 7062529-ME Status: Completed | 16d LLC | $9.4K |
#7058863-EL Electrical · Electrical ELECTRICAL FOR ELEVATOR MODERNIZATION Status: Completed | 16d LLC | $10.3K | |
| applied Nov 22 | #7057694-CY Conveyance · Trade Alterations include: new controller, power unit, battery lowering, rupture valve, door operator, clutch, 3D edge door detector, pickups, interlocks, new car and hall fixtures, traveling cable, car top inspection station, car top railing, car top lighting, alarm bell, emergency light, phone,… Status: Completed | ELTEC Systems LLC | $157K |