Commercial General Building, Electrical, Elevator, Fire Protection, Hvac/Mechanical, Sign work permitted February 17, 2025, with 35 permits through May 28, 2026, declaring $3,114,670 of work. Contractor on record: Cochran Incorporated.
low voltage - audio/visual (part of a TI where other contractors are pulling permits for other systems) 2 parts to project: 1. upgrade existing systems in 2 conference rooms, minimal construction 2. new systems as part of office suite remodel reconfigure existing IDF equipment racks, pull new cable through raised floor to new/modified low voltage endpoints including speakers, cameras, etc.
Seattle permit records name Cochran Incorporated, McKinstry Co LLC and BSI Tech LLC as the contractors on this project, among 9 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
35 permits issued Feb 17 – May 28, newest first.
Commercial and multifamily, biggest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
#7145213-EL Electrical · Electrical Install low voltage lock cabling for a service request Status: Issued | Cochran Inc | — | |
#7135423-BP Boiler/Pressure Vessel · Trade Replacing (4) gas boilers, like-kind. National Board # 102092-G-25-2132. Future decarbonization plan required before final inspection. Status: Completed | McKinstry Co LLC | $68K | |
#7135425-BP Boiler/Pressure Vessel · Trade Replacing (4) gas boilers, like-kind. National Board # 102093-G-25-2133. Future decarbonization plan required before final inspection. Status: Completed | McKinstry Co LLC | $68K | |
#7135429-BP Boiler/Pressure Vessel · Trade Replacing (4) gas boilers, like-for-like. National Board # 10291-G-25-2131. Future decarbonization plan required before final inspection. Status: Completed | McKinstry Co LLC | $68K | |
#7135438-BP Boiler/Pressure Vessel · Trade Replacing (4) gas boilers, like-kind. National Board # 10297-G-25-2127. Future decarbonization plan required before final inspection. Status: Issued | McKinstry Co LLC | $68K | |
| applied Sep 30 | #7101650-ME Mechanical · Trade Remove and replace existing rooftop (4) gas-fired boilers, per plan Status: Completed | McKinstry Co LLC | $324K |
| applied Jan 8 | #7121537-CN Addition/Alteration · Building Construct tenant improvement for break room at room S2-200 level S2 in exiting office building per plan. Status: Completed | Not published | $500 |
#7119794-EL Electrical · Electrical Disconnect 4 existing gas boilers and connect 4 new gas boilers to existing circuits. Status: Completed | McKinstry Co LLC | $15K | |
#7119221-EL Electrical · Electrical HVAC Low Voltage Wiring Status: Completed | Datskiy Electric LLC | $3.1K | |
#7117541-EL Electrical · Electrical Modification to existing fire alarm system. Remove and reinstall (4) devices. This is a joint venture between Johnson Controls and Cochran Electric. Status: Completed | Johnson Controls Fire Protection | $3.6K | |
#7115840-EL Electrical · Electrical Adding a card reader and door contact to a door on the 6th Floor Status: Issued | Cochran Inc | $4K | |
| applied Oct 28 | #7112326-SB Sign, Awning and Canopy · Trade Replace 2 sets of existing individual lettering with 2 flat non-illuminated signs. Located at corner of Harrison St & Republican. Northeast Corner. 10/21/25 SS: Revised Plans from applicant uploaded to portal for contractor. Status: Completed | Doty and Associates | $37K |
#7113458-EL Electrical · Electrical Removal and Re-installation of 169 Network Cameras. Reuse of existing cabling. Status: Completed | Cochran Inc | $344K | |
| applied Oct 21 | #7112612-ME Mechanical · Trade Install one new fan powered only vav, and relocate one existing VAV a few feet to make room for this new unit - Subject to Field Inspection (STFI) Status: Completed | McKinstry Co LLC | $22.8K |
#7108217-EL Electrical · Electrical Job # 528187 Reconfiguration of S2-200 Conference Room Status: Completed | Cochran Incorporated | $20K | |
| applied Sep 18 | #7107514-CN Addition/Alteration · Building Construct tenant improvements to portion of Level-S2 commercial office subject to field inspection (STFI) Status: Completed | Not published | $200K |
| applied Sep 10 | #7105454-CY Conveyance · Trade remove and replace flooring in accordance with applicable codes and standards. weight differential is less than +/- 5 % EQP-SI-08402 / EQP-CY-07485 (2021 SBC = 2019 A17.1 = 2023 NEC/SEC = 2020 A18.1) Status: Issued | Otis Elevator | $3.5K |
#7104775-EL Electrical · Electrical Phase 2 updates to North 6 suite. Job # 526659 Status: Completed | Cochran Incorporated | $70K | |
#7104914-EL Electrical · Electrical Job 4005732: Demo & Make save power. Demo (1) track fixture and reinstall (3) track fixtures. (1) floor box, (1) 120v 20a receptacle, (2) data pathway. Site contact: Ryan Hooper (425) 531-5771 Status: Completed | Prime Electric | $1.4K | |
| applied Jul 14 | #7095822-FS Fire Sprinkler and Suppression · Trade Tenant improvement involving 10 fire sprinkler heads. Status: Completed | McKinstry Co. LLC | $2.7K |
| applied Aug 7 | #7099926-ME Mechanical · Trade ** STFI ** Revision of diffusers and grilles and addition of (2) cooling-only VAV boxes (no heat). Status: Completed | McKinstry Co LLC | $31.9K |
#7100390-EL Electrical · Electrical Like in kind replace of Halogen track and pendant lighting to LED in atrium Status: Completed | Cochran Incorporated | $55K | |
#7096839-EL Electrical · Electrical Refreshing a complex audiovisual system in a triple room combinable space. New LV cabling, ceiling devices, re-wiring of existing devices, and equipment rack work. Status: Completed | BSI Tech LLC | $392K | |
| applied Jun 30 | #7093947-CN Addition/Alteration · Building Install and hang an art installation in an existing space from existing rigging points subject to field inspection STFI Status: Completed | Not published | $15K |
| applied Apr 17 | #7080131-CN Addition/Alteration · Building Construct alterations to existing office building at level 6 per plan. Status: Completed | Not published | $324K |
| applied Apr 8 | #7078515-ME Mechanical · Trade ** STFI ** Revision of diffusers and grilles at Gates Foundation. Status: Completed | McKinstry Co LLC | $8.7K |
| applied Mar 31 | #7076852-SB Sign, Awning and Canopy · Trade SUPPLY A NEW NON-ILLUMINATED SIGN TO COVER UP EXISTING CARVED STONE LETTERING. Status: Completed | CK Doty & Associates of WA Inc | $55K |
#7074933-EL Electrical · Electrical Relocating 6 Fire Alarm Devices on North 6 for Phase 1 remodel. Job # 526659 Status: Completed | Cochran Incorporated | $1.5K | |
#7074703-EL Electrical · Electrical low voltage - audio/visual (part of a TI where other contractors are pulling permits for other systems) 2 parts to project: 1. upgrade existing systems in 2 conference rooms, minimal construction 2. new systems as part of office suite remodel reconfigure existing IDF equipment racks, pull new… Status: Completed | BSI Tech LLC | $612K | |
#7074054-EL Electrical · Electrical General Security Service Status: Completed | Cochran Inc | $5K | |
#7072600-EL Electrical · Electrical Installation Access Control (1) Card Reader & (1) Camera Status: Completed | Cochran Inc | $13K | |
#7071882-EL Electrical · Electrical Partial remodel of executive suite Status: Completed | Cochran Incorporated | $100K | |
| applied Feb 14 | #7070605-CN Addition/Alteration · Building Tenant improvement to 6th floor of existing commercial building subject to field inspection (STFI) Status: Completed | Not published | $450K |
#7070991-EL Electrical · Electrical PERFORM 2 HOUR LOAD BANK TEST ON STANDBY GENERATOR ONLY. DISCONNECT BUILDING CONDUCTORS, CONNECT LOAD BANK, PERFORM LOAD BANK TEST, LAND AND TORQUE ORIGINAL BUILDING CONDUCTORS. Status: Completed | Not published | $2.1K | |
#7070992-EL Electrical · Electrical PERFORM 2 HOUR LOAD BANK TEST ON STANDBY GENERATOR ONLY. DISCONNECT BUILDING CONDUCTORS, CONNECT LOAD BANK, PERFORM LOAD BANK TEST, LAND AND TORQUE ORIGINAL BUILDING CONDUCTORS. Status: Completed | Not published | $2.1K |