Commercial General Building, Electrical, Fire Protection, Sign work permitted December 20, 2024, with 15 permits through September 2, 2026, declaring $342,149 of work. Contractor on record: Prime Electric.
Construct blanket permit tenant improvements to Amazon SEA37 on the fifth floor of existing commercial building per plan.
Seattle permit records name Prime Electric, Teknon Infrastructure Services and Holaday Parks Inc as the contractors on this project, among 6 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
15 permits issued Dec 20 – Sep 2, newest first.
| Issued | Permit | Contractor | Value |
|---|
Commercial and multifamily, biggest first.
#7160992-EL Electrical · Electrical Adding network cabling to support data needs of office retrofit. Status: Issued | Teknon Infrastructure Services | — | |
#7156887-EL Electrical · Electrical Low Voltage, 1 VAV connection and 1 Stat relocation, L5 Status: Completed | Holaday Parks Inc | — | |
| applied Jul 10 | #7152326-CN Addition/Alteration · Building Construct interior only tenant improvement on Level 5 to install (2) phone booths. Subject to field inspection-STFI Status: Completed | Not published | $15K |
| applied Jun 11 | #7147036-BK Tenant Improvment · Building Construct blanket permit tenant improvements to Amazon SEA37 on the fifth floor of existing commercial building per plan. Status: Completed | Not published | $287K |
#7155083-FS Fire Sprinkler and Suppression · Trade TENANT IMPROVEMENT - ADD/RELOCATE FIRE SPRINKLERS FOR T.I. WALLS. PIPE SIZING AND K FACTOR OF NEW HEADS TO MATCH EXISTING, NO IMPACTS TO EXISTING HYDRAULIC CALCULATIONS. NO CHANGE OF OCCUPANCY FROM PREVIOUS BUILD. PATRIFP099CF. (5) Heads. Status: Completed | Not published | $3.6K | |
#7150859-EL Electrical · Electrical Adding 6 devices Status: Issued | Guardian Security Systems Inc | — | |
#7149028-EL Electrical · Electrical Upgrades to power and lighting and fire alarm for VP office on Level 5 Status: Issued | Prime Electric | — | |
#7149029-EL Electrical · Electrical Upgrades to power and lighting for VP office Status: Completed | Prime Electric | — | |
| applied May 14 | #7143372-CN Addition/Alteration · Building Construct tenant improvement to East portion of level 2 office space subject to field inspection STFI. Status: Issued | Not published | $5K |
#7120929-EL Electrical · Electrical BCP 65037. Low Volt Cable Install Status: Issued | BlueCore Power LLC | $3K | |
#7110857-FS Fire Sprinkler and Suppression · Trade TENANT IMPROVEMENT - ADD/RELOCATE FIRE SPRINKLERS FOR T.I. WALLS AND LIGHTS. PATRIFP099CF. (5) Heads. Status: Issued | Not published | $2.5K | |
| applied Jul 28 | #7097118-SB Sign, Awning and Canopy · Trade REPLACE EXISTING UMPQUA BANK SIGNS WITH NEW COLUMBIA BANK SIGNS Status: Completed | Heath Northwest | $3K |
#7084137-EL Electrical · Electrical We will be adding eight (8) monitor points to the BDA system. This will require the addition of (1) new fire cabinet, (1) motherboard, and (4) dual input modules. 5/7/2025 added Industrial Communications as contractor Status: Completed | Not published | $14.3K | |
#7071610-EL Electrical · Electrical Provide (10) quad receptacles on Floors 2-6-Seq Job #305963 Status: Completed | Not published | $9K | |
#7062031-EL Electrical · Electrical Job 7011217: Install (5) duplex receptacles. Contact: Shawn Boulger 425-457-2224 Status: Completed | Prime Electric | $2.5K |