Commercial General Building, Electrical, Elevator, Fire Protection, Hvac/Mechanical work permitted December 4, 2024, with 23 permits through May 14, 2026, declaring $2,417,623 of work. Contractor on record: Prime Electric.
Replacement of air terminal devices and installation of some ductwork, per plans
Seattle permit records name Prime Electric, McKinstry Co LLC and Macdonald Miller Facility Solutions LLC as the contractors on this project, among 13 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
23 permits issued Dec 4 – May 14, newest first.
| Issued |
|---|
Commercial and multifamily, biggest first.
| Permit |
|---|
| Contractor |
|---|
| Value |
|---|
#7142298-BP Boiler/Pressure Vessel · Trade We are replacing the failed heat exchanger and associated gaskets and components Status: Completed | Macdonald Miller Facility Solutions LLC | $22.6K | |
#7139557-EL Electrical · Electrical Patch Panels E219, E510, E517 job #1026220, Furnish and install Cat6A cabling and (2) patch panels between tenant rooms and IDF locations. Includes routing through pathways. NOT terminations, UW SLU Building 3 (SLU3), Site contact: Kolten DeKoker 425-890-0338 Status: Issued | Prime Electric | — | |
| applied Mar 13 | #7130856-ME Mechanical · Trade Rework space for new tenant space layout. Remove existing diffusers and reinstall as needed for new space. (7) Supply Diffusers (4) linier and (3) supply (4) return air grilles. subject to field inspections (STFI) Status: Completed | Vital Mechanical Inc | $21K |
#7132526-EL Electrical · Electrical Add reader, REX and contact to door F207, connect to existing panel Status: Completed | Pavion | — | |
#7128681-EL Electrical · Electrical Status: Issued | Red Hawk Fire Protection | — | |
#7126767-EL Electrical · Electrical Status: Completed | Vital Mechanical Inc | — | |
#7126443-EL Electrical · Electrical Status: Completed | Teknon Infrastructure Services | — | |
#7123678-FS Fire Sprinkler and Suppression · Trade Add and relocate fire sprinklers as required for tenant improvements. Status: Completed | Patriot Fire Protection | $6.2K | |
#7121244-EL Electrical · Electrical Install misc. power and lighting for TI. Status: Completed | Olsen Electric Inc | $170K | |
| applied Oct 14 | #7109473-CN Addition/Alteration · Building Construct tenant improvement for office (UW Ophthalmology) in Suite F207 of existing office building per plan. Status: Completed | Not published | $250K |
| applied Oct 23 | #7113233-CY Conveyance · Trade install new Otis Glide A Door operator EQP-SI-08665 / EQP-CY-07744 (2021 SBC = 2019 A17.1 = 2023 NEC/SEC = 2020 A18.1) Status: Issued | Artline | $34K |
#7108818-EL Electrical · Electrical Job # 1024273: Install (1) 208v outlet to Emergency Power, 750 Republican St. Contact: Kolten De Koker (425) 890-0338; [8/31/26 RN Renewal/Reinstatement fee added] Status: Completed | Prime Electric | $1.4K | |
#7107774-EL Electrical · Electrical Pull and terminate all low-voltage wiring to the SPSWLED and FRM-1 devices. - Mount and connect the SPSWLED horn strobe and FRM-1 relay modules. - Program the devices into the fire alarm control panel (FACP) to ensure proper operation: - SPSWLED to activate on alarm condition. - FRM-1 relays to… Status: Completed | Everon LLC | $3.1K | |
#7105702-EL Electrical · Electrical Modifying access control system for the 7th floor lab UW MEd, devices and panel trim Status: Completed | Convergint | $40K | |
#7104171-EL Electrical · Electrical Job 1024037: Provide and install (3) 30A NEMA L6-30 twist lock emergency outlets in for new servers. Includes new wire, junction box, supports, and associated fittings. New outlets shall be installed in existing wire mold. Includes (3) new Siemens breakers in existing panel. Site contact: Kolten… Status: Issued | Prime Electric | $2.6K | |
#7103920-EL Electrical · Electrical 126998-003- Provide rough in conduit for door access controls. (1) door. Rough in boxes for (2) cameras. Install (1) new exit sign. (Closed out by PJR 09-25-25) Status: Closed | McKinstry Co LLC | $10K | |
#7103291-EL Electrical · Electrical Job Number - 1023350 Description - Provide labor and material for installation of (2) Surge Protection Devices to two panels. Contact - Kolten Dekoker 425-890-4690 Status: Completed | Prime Electric | $6.2K | |
#7101362-EL Electrical · Electrical Re-routing existing circuits in interstitial to accommodate duct diffuser relocates in 7 areas Add 15 120 volt circuits for ATS dampers/valves, controllers, and door power. Add 1 large enclosure and 18 500va transformer enclosures associated with ATS dampers Relocating a light fixture and… Status: Completed | McKinstry Co LLC | $120K | |
| applied May 30 | #7075868-CN Addition/Alteration · Building Construct tenant improvements to existing commercial building at level 7 per plan. Status: Completed | Not published | $705K |
#7094847-EL Electrical · Electrical Mother's Room (3rd Floor E): Relocate existing outlet to new casework installation Replace existing can light with new fixture to match others in the space Shower Room (5th Floor E): Relocate outlet to adjacent wall Status: Completed | Tapps Electric | $2K | |
| applied May 15 | #7078128-ME Mechanical · Trade Replacement of air terminal devices and installation of some ductwork, per plans Status: Completed | McKinstry Co LLC | $1M |
#7086061-EL Electrical · Electrical Job 1023229: Provide and install (1) 20A 120v hospital grade emergency outlet + breaker in Building F by pharmacy - panel SBP-F-01-01. Contact: Kolten De Koker 425-890-0338; [8/31/26 RN Renewal/Reinstatement fee added and change of address] Status: Completed | Prime Electric | $1K | |
#7059363-BP Boiler/Pressure Vessel · Trade replacing heat exchanger Status: Completed | Macdonald Miller Facility Solutions LLC | $22.6K |