Get ProEvery project in every city · from $79/mo
Get Procommercial project · Seattle, WA
Commercial General Building, Electrical, Elevator, Fire Protection, Hvac/Mechanical work permitted February 27, 2025, with 15 permits through March 25, 2026, declaring $2,807,400 of work. Contractor on record: Prime Electric.
Remodel of sanctuary, foyer, and basement. Panel replacement, power and lighting. Contact: James Kawabata 425-351-2120 [ 1-12-26 Revision Approved ]
Seattle permit records name Prime Electric, Kone Inc (Primary) and Convergint Technologies as the contractors on this project, among 7 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
15 permits issued Feb 27 – Mar 25, newest first.
| Issued |
|---|
Commercial and multifamily, biggest first.
| Permit |
|---|
| Contractor |
|---|
| Value |
|---|
#7135101-EL Electrical · Electrical TDHS - Job 8000976: Disconnect and reconnect skylight shutter power. Status: Completed | Prime Electric | — | |
#7134674-EL Electrical · Electrical TDHS- Job # 8000976, Install three lights and one occ/switch. Site Contact: Phil Reed 425-864-5753 Status: Completed | Prime Electric | — | |
| applied Jan 2 | #7123206-FS Fire Sprinkler and Suppression · Trade Connecting to and extending existing Temple fire sprinkler system to protect the Chapel. Status: Completed | Not published | $65K |
| applied Jan 28 | #7119742-CY Conveyance · Trade New Installation - Portable wheelchair lift 6960304-CN (Construction Permit) 2018 SBC = 2020 SEC = 2019 A17.1 = 2017 A18.1 Status: Completed | Kone Inc (Primary) | $11K |
#7126951-EL Electrical · Electrical Status: Completed | Convergint Technologies | — | |
#7114390-EL Electrical · Electrical TDHS Sellen - Job 5005062: Provide and install CAT cable to new camera adds, wireless access points, and card readers on levels 1 and 2. Site contact: Sharla Spear (425) 429-5652 Status: Completed | Prime Electric | $10K | |
#7114133-EL Electrical · Electrical Class 2LV Controls: (1) new JACE and IP controller. (4) SF's with VFD control. (4) Tstat relocates (1) Sanctuary Zone Sensor/ new conduit and control wiring for: -VF-1 with IP controller, start/stop/status, and damper interlock wiring. Status: Completed | Static Energy, Inc | $6.4K | |
| applied Apr 21 | #7081769-FS Fire Sprinkler and Suppression · Trade Design and install new automatic sprinkler system within existing Temple De Hirsch building. Riser room located in the basement of adjacent school building. Status: Issued | Patriot Fire Protection | $135K |
#7105094-EL Electrical · Electrical Audio Visual Systems for Remodel of Jewish Temple ;[3/6/2026 JBC Added AVI Systems dba FORTE to Permit] Status: Completed | AVI Systems dba FORTE | $350K | |
| applied Jul 24 | #7098121-CN Addition/Alteration · Building Interior alteration to existing institution subject to field inspection (STFI) Status: Completed | Not published | $140K |
| applied Jun 9 | #7089866-FS Fire Sprinkler and Suppression · Trade UNDERGROUND ONLY Install 100-lf of 6-in Fire protection service from new meter to existing building. Status: Completed | Temple De Hirsch Sinai | $15K |
| applied Feb 4 | #7065044-ME Mechanical · Trade The mechanical scope includes a new supply fan array and filtration in the existing AHU equipment, new supply ductwork and diffusers in existing Sanctuary, new rooftop exhaust fan in Sanctuary, and new exhaust ductwork and diffusers in new restrooms - per plans. Status: Completed | Not published | $325K |
| applied May 14 | #7085523-EL Electrical · Electrical Remodel of sanctuary, foyer, and basement. Panel replacement, power and lighting. Contact: James Kawabata 425-351-2120 [ 1-12-26 Revision Approved ] Status: Completed | Prime Electric | $1M |
| applied Jul 30 | #6960304-CN Addition/Alteration · Building Construct alterations to portions of an institutional building including exterior access and site work per plans. Status: Completed | Not published | $700K |
#7072828-EL Electrical · Electrical Demo light fixtures and some power devices. Contact: James Kawabata 425-351-2120 Status: Completed | Prime Electric | $50K |