Commercial General Building, Electrical, Fire Protection, Hvac/Mechanical work permitted January 22, 2025, with 10 permits through October 2, 2026, declaring $354,494 of work. Contractor on record: Prime Electric.
Get new commercial permits near 98109 or Seattle, free weekly email
Construct alterations to install pre-manufactured phone booths at 2nd 3rd 4th 5th and 6th floor levels of commercial office building [WESTLAKE TERRY WEST BUILDING] subject to field inspection [STFI].
Seattle permit records name Prime Electric, Holmes Electric Company and Evergreen Power Systems, Inc as the contractors on this project, among 4 contractors in all.
10 permits issued Jan 22 – Oct 2, newest first.
| Issued | Permit | Contractor | Value |
|---|
Commercial and multifamily, biggest first.
#7165607-EL Electrical · Electrical 79330 - disconnect (4) feeds to existing pumps and reconnect after replacement by others Status: Issued | Holmes Electric Company | — | |
#7161680-EL Electrical · Electrical 320 Westlake Ave N - Job 1027653: Install (3) duplex GFCI protected NEMA 5-20 receptacles and (3) dedicated circuits one at each kitchenette on levels 03, 04 and 06. Status: Issued | Prime Electric | — | |
| applied Aug 21 | #7102866-EL Electrical · Electrical We are installing (11) ceiling strobes as a joint venture with Prime Electric. Status: Completed | Prime Electric | $15.2K |
| applied Aug 1 | #7099541-FS Fire Sprinkler and Suppression · Trade TENANT IMPROVEMENT - ADD FIRE SPRINKLERS FOR T.I. ADDITION OF PHONE BOOTHS. NO CHANGES TO EXISTING COVERAGE. PATRIFP099CF. (11) Heads. Status: Completed | Not published | $11.3K |
| applied Jun 17 | #7084719-CN Addition/Alteration · Building Construct alterations to minor telecommunications facilities [AT&T] at rooftop antennas and equipment pen for mixed-use office building [WESTLAKE TERRY WEST BLDG] per plan. Status: Issued | Not published | $30K |
| applied Jun 26 | #7093334-CN Addition/Alteration · Building Construct alterations to install pre-manufactured phone booths at 2nd 3rd 4th 5th and 6th floor levels of commercial office building [WESTLAKE TERRY WEST BUILDING] subject to field inspection [STFI]. Status: Completed | Not published | $220K |
#7090360-EL Electrical · Electrical Job 4005752: Adding (7) general use duplex receptacle. Site contact: Shawn Boulger (425) 457-2224 Status: Completed | Prime Electric | $2.5K | |
#7088612-EL Electrical · Electrical 20170 - Bocz Salon - add/alter lighting, outlets, switches. Status: Completed | Evergreen Power Systems, Inc | $14K | |
#7086644-BP Boiler/Pressure Vessel · Trade This site has an existing Hydro Therm KN-10 cast iron sectional condensing boiler that has failed and required immediate replacement. The suggested replacement boiler is a Lochinvar Crest FTXL 1000 with a 10:1 turndown at 98.3% efficiency. This boiler is a like in kind at a higher efficiency and a… Status: Completed | Mesa Energy Systems | $60K | |
#7066450-EL Electrical · Electrical Adding (3) general use receptacles. Job #4005299. Prime Electric site Contact Shawn Boulger 425-457-2224 Status: Completed | Prime Electric | $1.5K |