Commercial General Building, Electrical, Hvac/Mechanical, Roofing work permitted April 8, 2025, with 10 permits through September 28, 2026, declaring $22,339,912 of work. Contractor on record: Cochran, Inc..
Construct alterations to existing transit yard (King County Atlantic Trolley Base) per plan.
Seattle permit records name Cochran, Inc., Washington Electrical Contracting LLC and NuuCo Electric as the contractors on this project, among 4 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
10 permits issued Apr 8 – Sep 28, newest first.
| Issued | Permit | Contractor | Value |
|---|
Commercial and multifamily, biggest first.
| applied Sep 18 | #7163278-EL Electrical · Electrical King County Metro will install (2) 30-amp 2-pole breakers in existing panels, and (4) L6-30 receptacles with conduit and wiring. [9/28/26 KEF - Plan set approved. Work to be self-performed by KC Metro.] Status: Issued | Not published | $500 |
#7148445-EL Electrical · Electrical Install empty pathway for data contractor (Cochran) Status: Completed | Washington Electrical Contracting LLC | — | |
#7146413-EL Electrical · Electrical 1 Cat6A to 6 locations for WAP's Status: Completed | Cochran, Inc. | — | |
#7146418-EL Electrical · Electrical 1 Cat6A to 18 WAP locations Status: Completed | Cochran, Inc. | — | |
| applied Feb 25 | #7123770-ME Mechanical · Trade Alterations to mechanical system on existing industrial building, per plans. Status: Issued | Not published | $687K |
#7132918-EL Electrical · Electrical King County Metro will be adding two 2-pole 30-amp receptacles, their respective circuit breakers on existing panelboards, and conduit+ wiring. Status: Issued | Not published | — | |
#7117488-RR Roof · Roof Remove existing built up roofing to concrete deck. Install new built up roofing. Status: Completed | Not published | $127K | |
| applied Sep 5 | #7105252-EL Electrical · Electrical Excavate Duct bank 3517lf and install 31 Type 233 Vaults and approx. 24,000lf of conduit schedule 80 Status: Issued | NuuCo Electric | $521K |
| applied Apr 7 | #6887836-CN Addition/Alteration · Building Construct alterations to existing transit yard (King County Atlantic Trolley Base) per plan. Status: Issued | Not published | $21M |
#7079766-EL Electrical · Electrical 76368-Add (1) circuit for switch and (2) Receptacles. Status: Completed | Holmes Electric Company | $5K |