Commercial General Building, Electrical work permitted October 30, 2024, with 6 permits through April 15, 2026, declaring $25,097,634 of work. Contractor on record: Shimmick Construction.
Installing two(2) 13.8kv-6.6kV, 7.5mVA shore-power substations to power container vessels while at Terminal 18 loading/unloading cargo containers. The shore-power are substation will be manufactured walk-in enclosures housing the 13.8kV and 6.6kV switchgear, transformer installed/mounted outside walk-in enclosure. And install five(5) 6.6kV shore-power connections at the bull-rail for container ship connection. [7/1/25 BGO - Approved Plan Set] **Renewed 6/9/26, EC**
Seattle permit records name Shimmick Construction as the contractor on this project.
Phone numbers and the property owner are included with Pro, where the city publishes them.
6 permits issued Oct 30 – Apr 15, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Sep 10 | #7096052-CN |
Commercial and multifamily, biggest first.
Addition/Alteration · Building
Construct middle substation and associated power vault and sitework per plan. [Construct shore power vaults substations and associated site alterations for container terminal [PORT OF SEATTLE TERMINAL 18] per plan. Review and processing for (3) construction records under 7046509-CN.]
Status: Issued
| Not published |
| $11M |
| applied Sep 10 | #7096053-CN Addition/Alteration · Building Construct south substation and associated power vault and sitework per plan. [Construct shore power vaults substations and associated site alterations for container terminal [PORT OF SEATTLE TERMINAL 18] per plan. Review and processing for (3) construction records under 7046509-CN.] Status: Issued | Not published | $11M |
| applied Jun 17 | #7046509-CN Addition/Alteration · Building Construct north substation and associated power vault and sitework per plan. [Construct shore power vaults substations and associated site alterations for container terminal [PORT OF SEATTLE TERMINAL 18] per plan. Review and processing for (3) construction records under 7046509-CN.] Status: Issued | Not published | $11M |
#7125098-EL Electrical · Electrical Providing temporary power( 200 amps) for the office trailer for the Port of Seattle- T-18 Shore Power Project. Status: Completed | Shimmick Construction | — |
| applied Jun 17 | #7091666-EL Electrical · Electrical Installing two(2) 13.8kv-6.6kV, 7.5mVA shore-power substations to power container vessels while at Terminal 18 loading/unloading cargo containers. The shore-power are substation will be manufactured walk-in enclosures housing the 13.8kV and 6.6kV switchgear, transformer installed/mounted outside… Status: Issued | Not published | $12.8M |
| applied Jul 19 | #7027614-CN Addition/Alteration · Building Construct alterations to upgrade existing radiation portal monitors signage signals and supports at truck and rail exit gates of Terminal 18 per plan. Status: Issued | Not published | $1.3M |