Commercial Electrical, Hvac/Mechanical work permitted December 29, 2025, with 6 permits through October 7, 2026, declaring $8,769 of work. Contractor on record: CTS.
Seattle permit records name CTS, Cochran, Inc. and Pacific Power Group as the contractors on this project, among 4 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
The contractor on 1 permit issued in the last 30 days is included with Pro.
See the contractor6 permits issued Dec 29 – Oct 7, newest first.
Commercial and multifamily, biggest first.
| Issued | Permit | Contractor | Value |
|---|
#7166314-EL Electrical · Electrical adding five dedicated ckts.to 3rd floor. extending 5 ckts. hooking up furniture on 4th floor. 10/7/2026 address change from 418 S JACKSON ST [C.Kenefick 10/26/2026 - address changed again to 315 5th Ave S. No service work this permit.] Status: Completed | Contractor with Pro | — | |
#7162842-EL Electrical · Electrical ADDING 203 CAT6 CABLES TO NEW TIA SPACE, FLOORS 3 & 4 Status: Completed | CTS | — | |
#7160811-EL Electrical · Electrical 86457 - Replace/repair (8) exit signs Status: Completed | Cochran, Inc. | — | |
#7157688-EL Electrical · Electrical Installation of [001] 24 strand OSP Riser Rated SM fiber from IDS to Bld. 315. [002] 1RU FIBER ENCLOSURE [002] 24-FIBER MOLDED SPLICE TRAY [001] FUSION SPLICE SLEEVE, 60mm (BAG OF 50) [004] OS2 SINGLE MODE LC FIBER PIGTAIL KIT (TIA 1-12 COLOR) [002] SM (OS2), QUAD LC, 24 FIBER BULKHEAD Status: Completed | CTS | — | |
#7124639-EL Electrical · Electrical LOAD BANK TESTING ON BACK UP ELCTRIC GENERATOR - SR00121113 Status: Issued | Pacific Power Group | — | |
| applied Dec 23 | #7122118-ME Mechanical · Trade Replacement of WSHP Status: Completed | PSR Mechanical | $8.8K |