Commercial General Building, Electrical, Fire Protection, Hvac/Mechanical work permitted December 13, 2024, with 22 permits through February 25, 2026, declaring $1,148,804 of work. Contractor on record: CTS.
Construct blanket permit tenant improvements to Wellpoint on the third floor of existing commercial building per plan.
Seattle permit records name CTS, Columbia Fire and Holaday Parks Inc as the contractors on this project, among 13 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
22 permits issued Dec 13 – Feb 25, newest first.
| Issued | Permit | Contractor | Value |
|---|
Commercial and multifamily, biggest first.
#7130996-FS Fire Sprinkler and Suppression · Trade Modify the existing fire sprinkler system to accommodate the wall and ceiling changes. Status: Completed | Columbia Fire | $5.4K |
#7123259-EL Electrical · Electrical Replace like in kind batteries in UPS cabinet. All existing Wiring and load will remain the same. No modifications to existing system. Replacement of spent batteries. Battery Cabinet breaker is 100amp. Status: Completed | Enersys Delaware Inc | — |
#7120928-EL Electrical · Electrical BCP 65036. Low Volt Cable Install Status: Issued | BlueCore Power LLC | $3K |
#7119911-EL Electrical · Electrical Provide services to contract an electrical contractor to install [003] new duplex power outlets to [003] locations within the 9th and 11th floors as shown on supplied drawings. Supply and install materials to support an open pathway, such as J-hooks and hangers where possible. Provide as-built… Status: Completed | CTS | $3.2K |
#7115994-EL Electrical · Electrical Security Job 836472 Status: Completed | EC Electric | $23.5K |
| applied Oct 16 | #7112220-RF Refrigeration · Trade Install refrigeration piping for new VRF split system (mechanical permit #7070938-ME) Status: Completed | Enviromech | $41K |
#7108326-EL Electrical · Electrical Pathway for data cabling Status: Completed | Fiber Force LLC | $2.3K |
#7107875-EL Electrical · Electrical Install of alarm panel with hold-up button device rerouting cable for one access door and camera Status: Completed | Convergint Technologies | $17.1K |
#7106969-EL Electrical · Electrical Supply and install 4pr UTP Cat6A cable from appropriate MDF/IDF to each WAP location. Create and implement a labeling scheme that is compliant with EIA/TIA 606 and per customer's approval. Update as-built drawings to show exact location of all new cable drops and label scheme assigned to each… Status: Issued | CTS | $90K |
| applied Jul 16 | #7096396-EL Electrical · Electrical Adding 16 new speaker/strobes and 6 new strobes to suites 300 and 300B. Status: Completed | OEG, Inc | $17.6K |
#7100588-EL Electrical · Electrical Supply and install [241] Cat6 cables to approximately [128] new locations throughout the building's 2nd floor. Terminate new data cables within IDF locations as specified to new 48 port patch panels. Terminate new data cables at workstation & AP locations with Cat6 RJ45 inserts. Test all new data… Status: Completed | CTS | $80.2K |
#7096825-EL Electrical · Electrical Installation of Low Voltage Conferencing Equipment in the meeting room Status: Completed | Avi-SPL LLC | $50K |
| applied Jun 9 | #7089946-FS Fire Sprinkler and Suppression · Trade Modify the existing Fire sprinkler system to accommodate the new walls and ceilings per the architectural drawings Status: Completed | Columbia Fire | $11.1K |
#7094336-EL Electrical · Electrical LV Energy Management Controls / Adding 2 Devices. Status: Completed | Holaday Parks Inc | $1K |
| applied Jun 25 | #7087201-ME Mechanical · Trade Add (2) VAV boxes with electric heat. Modify existing ductwork as needed for new layout per plans Status: Completed | Holaday Parks Inc | $30K |
| applied Jun 24 | #7092570-ME Mechanical · Trade Relocate 6 diffusers. subject to field inspections. (STFI) Status: Completed | Not published | $5K |
#7090333-EL Electrical · Electrical Tenant Improvement using existing load centers and circuits. Furniture panel to panel connections x 24. Job# 438332 Status: Completed | Pride Electric, Inc | $55K |
| applied Mar 14 | #7075004-BK Tenant Improvment · Building Construct blanket permit tenant improvements to Wellpoint on the third floor of existing commercial building per plan. Status: Completed | Not published | $350K |
| applied Feb 6 | #7068959-BK Tenant Improvment · Building Construct blanket permit tenant improvements to future tenant on the third floor of existing commercial building per plan. Status: Completed | Not published | $96K |
#7074469-EL Electrical · Electrical Open Area: 1. Provide electrical support in removal of walls for the 3 offices. Remove electrical outlets and light switches as needed. Verify that electrical devices that are not being removed still have power, re-feed remaining devices if the circuit was interrupted during demo. 2. Remove (3)… Status: Completed | Thompson Electrical Constructors | $10.5K |
#7072059-EL Electrical · Electrical install 2 circuits, one for each office powered furniture section and one for a wall receptacle Status: Completed | Pride Electric, Inc | $3.2K |
#7060865-CN Addition/Alteration · Building Construct tenant improvements for office space on ground level of existing commercial building subject to field inspection (STFI) Status: Completed | Not published | $254K |