Commercial General Building, Fire Protection, Hvac/Mechanical, Plumbing work permitted June 5, 2025, with 25 permits through October 19, 2026, declaring $10,972,011 of work.
Get new commercial permits near 98405 or Tacoma, free weekly email
Project scope includes: Remodel of existing Sterile Processing spaces. Adding a cart washer to the Decontamination side and reworking the layout and flow of processing. Adding an additional pre-processing sink and ultrasonic cleaner to the Decon side. Adding a scope wash space and modifications to layout on Sterile area. Work includes replacement of flooring, wall finishes and wall protection, and patch and repair ceilings including MEP scope. Some existing storage spaces will be modified for support. **IF PLUMBING & MECHANICAL PLANS WERE SUBMITTED, THE BUILDING PERMIT ONLY COVERS PLAN…
Tacoma’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
25 permits issued Jun 5 – Oct 19, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Oct 15 |
Commercial and multifamily, biggest first.
#MECH26-0007 Building Adding a unit heater to new water heaters. Building permit reference BLDCA26-0271, plumbing permit reference PLMBC26-0209 Status: Permit Issued |
| Not published |
| $6.8K |
| applied Aug 27 | #BLDCA26-0271 Building · Alteration Remodel of existing Hot Water Heater room and Addition of new Process Hot Water Room for new water heaters. Work includes hot water piping from level 0B down to Level 0D. Scope included patch and repair walls, floors, and ceilings as needed to access chase spaces in Commercial Bldg. **SEPARATE… Status: Permit Issued | Not published | $1M |
| applied Oct 9 | #PLMBC26-0209 Building · Plumbing Remodel of existing Hot water heater room and addition of new process hot water room for new water heaters including hot water piping from level 0B down to level 0D. Building permit reference BLDCA26-0271 Status: Permit Issued | Not published | $116K |
| applied Sep 2 | #FIREC26-0185 Building · Fire Protection Fire Alarm TI- 0D tenant improvement. Updated notification and addition of duct detection. Status: Permit Issued | Not published | $4K |
| applied Aug 5 | #EFIREA26-0026 ePermit · Alarm E003 ceiling refresh removes one notification device in the ceiling to be install in same place with new ceiling tile. Status: Finaled | Not published | $800 |
| applied Jul 24 | #FIREC26-0146 Building · Fire Protection Install Panel notification and sprinkler monitoring devices being added. [KAISER PERMANENTE TACOMA TEMPORARY TRAILER. Status: Finaled | Not published | $2K |
| applied Jun 23 | #PLMBC26-0146 Building · Plumbing Installing electric hot water tanks, piping, and fixtures to serve SPD department. Associated building permit - BLDCA26-0071 Status: Finaled | Not published | $690K |
| applied Jun 8 | #PLMBC26-0129 Building · Plumbing Plumbing for temporary sterile processing trailer outside building front entry Status: Finaled | Not published | $125K |
| applied Jun 23 | #MECHC26-0139 Building · Mechanical Install AHU/ACCU-7, duct work & piping to terminal units, and fans to serve SPD department on level 0D. Install exhaust fan and louver on floor 2 for temp scope wash, reverting duct work back once remodel is complete. **Related to: BLDCA26-0071** Status: Permit Issued | Not published | $764K |
| applied Jun 11 | #BLDCN26-0026 Building · New Building Temporary trailer located outside the building front entry to support Sterile Processing needs while the Sterile Processing Department is under construction (this is directly connected to the BLDCA26-0071). Status: Final Inspection | Not published | $290K |
| applied Mar 13 | #BLDCA26-0071 Building · Alteration Project scope includes: Remodel of existing Sterile Processing spaces. Adding a cart washer to the Decontamination side and reworking the layout and flow of processing. Adding an additional pre-processing sink and ultrasonic cleaner to the Decon side. Adding a scope wash space and modifications to… Status: Permit Issued | Not published | $4.1M |
| applied Jun 9 | #FIREC26-0107 Building · Fire Protection Modify existing sprinkler system for new tenant improvement at Commercial building. Status: Permit Issued | Not published | $25K |
| applied May 28 | #PLMBC26-0119 Building · Plumbing Install floor sink in EQMEC 118 on level F Status: Permit Issued | Not published | $12.7K |
| applied Jun 8 | #EFIRES26-0009 ePermit · Sprinkler Installation of supply pipe to built in fire suppression system inside of temporary trailer, for the hospital's use during construction. Status: Finaled | Not published | $7.5K |
| applied Jun 3 | #EFIRES26-0008 ePermit · Sprinkler Relocate one existing sprinkler for ceiling adjustments. Status: Finaled | Not published | $1.8K |
| applied Mar 20 | #EFIREA26-0010 ePermit · Alarm Renovation to the PACU. Walls adjusted and moving fire alarm notification to cover areas. One new notification device from wall to ceiling mount. Status: Finaled | Not published | $4K |
| applied Mar 2 | #PLMBC26-0048 Building · Plumbing ** reviewed under BLDCA25-0312** Demo 3 sinks, Replace 2 sinks Status: Finaled | Not published | $6K |
| applied Dec 16 | #MECHC25-0316 Building · Mechanical INSTALLATION OF 3 NEW TERMINAL UNITS Status: Finaled | Not published | $11K |
| applied Oct 2 | #BLDCA25-0312 Building · Alteration Removal/replacement of existing casework in Staff Lounge, enlargement of Procedure Room, addition of Pre-Op holding bay, removal and replacement of sink in Soiled Utility and conversion of a portion of the Waiting area into Equipment Storage. Additionally, floor replacement, wall enhancements and… Status: Finaled | Not published | $1.2M |
| applied Sep 26 | #FIREC25-0236 Building · Fire Protection Two new duct detectors and control relays to provide AHU-6 and AHU-8 detection and shutdown. New modules to be tied into existing SLC loop. One new speaker to be installed on level D and tied into existing speaker circuit. Status: Finaled | Not published | $4K |
| applied May 8 | #MECHC25-0133 Building · Mechanical Replace the building's chiller, add a low temperature chiller that serves the operating room and includes modifications to the HVAC serving the sterile processing department and MRI. Status: Finaled | Not published | $1.4M |
| applied Oct 24 | #BLDCA24-0418 Building · Alteration REPLACE CHILLER, ADD A LOW TEMPERATURE CHILLER THAT SERVES THE OPERATING ROOM, AND MODIFICATIONS TO THE HVAC SERVING THE STERILE PROCESSING DEPARTMENT AND MRI AT KAISER PERMANENTE. **MECHANICAL, ELECTRICAL AND PLUMBING SCOPES WILL REQUIRE SEPARATE PERMITS FOR FIXTURES AND A TPU PERMIT.** Status: Permit Issued | Not published | $897K |
| applied Aug 25 | #BLDCA25-0278 Building · Alteration Kaiser Permanente Tacoma Medical Center will be utilizing a Temporary MRI Trailer for the duration of their MRI Replacement project. It will be located in the drive loop at the building's front entrance. Status: Final Inspection | Not published | $48K |
| applied May 16 | #MECHC25-0136 Building · Mechanical Adding a Split-system unit to the WALAB space of the Kaiser Permanente clinic in Tacoma, WA. This will include one (1)M outdoor unit with two (2) heads inside the lab space. FLOOR: 1 | SUITE: WALAB***REFERENCE BLDG PERMIT# BLDCA25-0105*** Status: Finaled | Not published | $102K |
| applied Apr 9 | #BLDCA25-0105 Building · Alteration Replacement of lab equipment (Hematology and Chem-Immuno analyzer) and associated scope and anchorage at Kaiser Permanente Tacoma Medical Center. Status: Finaled | Not published | $98.2K |