How long commercial permits take in Tacoma, by trade
Median days from application to issue and median declared value, commercial and multifamily permits issued July 31, 2026 – October 29, 2026.
| Trade | Permits | Median days to issue | Median declared value |
|---|---|---|---|
| Building | 109 | 63 | $100K |
| Fire protection | 93 | 22 | $12.7K |
| HVAC / Mechanical | 75 | 30 | $20K |
| Plumbing | 66 | 30 | $12.3K |
| Signs | 26 | 35 | $5K |
| Roofing | 9 | 0 | $78.8K |
Counts only permits whose record includes an application date (390 of 390). Times depend on the city’s review track: express and over-the-counter trade permits often issue within days, new construction takes longer.