Commercial General Building, Electrical, Fire Protection work permitted December 20, 2024, with 12 permits through June 3, 2026, declaring $91,611 of work. Contractor on record: Entrance Controls Inc.
Construct blanket permit tenant improvements to the City of Seattle Office of Labor Standards on the third floor of existing commercial building per plan.
Seattle permit records name Entrance Controls Inc, SES, Inc and Prime Electric as the contractors on this project, among 9 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
12 permits issued Dec 20 – Jun 3, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
Commercial and multifamily, biggest first.
#7146027-EL Electrical · Electrical 26078 - Seattle Labor Standards Security Upgrade - Install intercoms Status: Completed |
| Entrance Controls Inc |
| — |
#7143793-EL Electrical · Electrical Install modular furniture Status: Completed | SES, Inc | — |
#7141830-EL Electrical · Electrical Addition/alteration of one circuit. 20A Status: Completed | Prime Electric | — |
#7141649-EL Electrical · Electrical (20) CAT6 wall drops plus (1) ceiling drop for a WAP to support the new office location for City of Seattle OLS. All runs will terminate in the IDF room 110 block. Status: Completed | PNTG LLC | — |
#7137239-EL Electrical · Electrical 05489929 - This is a modification to the existing Fire Alarm system project. The existing UIO board card will be relocated to the north elevator machine room. A new Smoke Detector will be installed in each elevator machine rooms (at North and South). Also, one Control Relay will be install for the… Status: Issued | Performance Systems, Puget Sound | — |
#7121638-FS Fire Sprinkler and Suppression · Trade modify the existing sprinkler system to accommodate new walls. Status: Completed | Columbia Fire | $2.6K |
#7117187-EL Electrical · Electrical Add 1 speaker strobe and relocate 1 strobe. Working with Far West Technologies Status: Completed | Red Hawk Fire Protection | $1.3K |
#7116280-EL Electrical · Electrical Installation of 17 new data cables for furniture Status: Completed | Not published | $7K |
#7115899-EL Electrical · Electrical Demo IDF and 29 station locations Status: Completed | Cochran, Inc. | $7.5K |
#7112850-EL Electrical · Electrical Tenant Improvement including. (1) New pendant light (3) Pendant relocates (3) Duplex receptacles (4) Furniture feed relocates (1) New Exit Sign (1) New fire alarm device Status: Completed | Not published | $6K |
| applied Aug 18 | #7102127-BK Tenant Improvment · Building Construct blanket permit tenant improvements to the City of Seattle Office of Labor Standards on the third floor of existing commercial building per plan. Status: Completed | Not published | $67K |
#7062055-EL Electrical · Electrical Load bank testing of emergency back up generator - 106705; [2/11/26 RN Closed permit, Closed Without Inspection] Status: Closed | Pacific Power Group | $250 |