Commercial General Building, Electrical, Elevator, Fire Protection, Hvac/Mechanical, Sign work permitted June 23, 2025, with 12 permits through September 23, 2026, declaring $4,121,250 of work. Contractor on record: Proficient Electric.
[CHANGE OF USE FROM OFFICE TO SELF STORAGE] Construct alteration to existing commercial building occupy per plan.
Seattle permit records name Proficient Electric, Kone Inc (Primary) and Cascade Signs and Graphics as the contractors on this project, among 4 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
12 permits issued Jun 23 – Sep 23, newest first.
Commercial and multifamily, biggest first.
| Issued | Permit | Contractor | Value |
|---|
#7164025-EL Electrical · Electrical prewire cameras and doors Status: Issued | Proficient Electric | — | |
#7149781-EL Electrical · Electrical Installation of Two-Way Communication System. Consists of 1 Master Station, 1 Power Supply, and 6 Call Boxes (2 each at Levels 2, 3, & 4) Status: Completed | Not published | — | |
| applied Apr 1 | #7136120-EL Electrical · Electrical TI - rewire lighting and outlets for storage units Status: Issued | Proficient Electric | $181K |
| applied May 19 | #7142774-SB Sign, Awning and Canopy · Trade Multiple signs being install. Sign A nonillum FCO letters on a backer with an LumenPulse externally illuminating it. Sign B is also nonillum FCO letters on a backer with an LumenPulse externally illuminating it. Sign C is channel letters on a backer internally illuminated. All with photocells.… Status: Issued | Cascade Signs and Graphics | $60K |
| applied Apr 17 | #7138919-EL Electrical · Electrical Install Fire Alarm system in renovated building Status: Issued | Not published | $38K |
| applied Mar 31 | #7135398-CY Conveyance · Trade New Installation Traction elevator 7046835-CN (Construction Permit) 2021 SBC = 2019 A17.1 = 2023 NEC/SEC = 2020 A18.1 Status: Issued | Kone Inc (Primary) | $269K |
| applied Apr 20 | #7139208-RF Refrigeration · Trade Adding 5 one ton heads and one 5 ton condenser and a branch box Status: Issued | JR mechanical | $5K |
| applied Jul 29 | #7098730-FS Fire Sprinkler and Suppression · Trade Installing new overhead sprinklers in existing building that is being converted to a self storage facility. Our work will start after the existing floor control valves on each level. Status: Issued | Not published | $250K |
| applied May 28 | #7046835-CN Addition/Alteration · Building [CHANGE OF USE FROM OFFICE TO SELF STORAGE] Construct alteration to existing commercial building occupy per plan. Status: Issued | Not published | $2.8M |
| applied Sep 24 | #7108411-CY Conveyance · Trade 800 Maynard Elevator Decommissioning for existing freight elevator (out of service). Please see scope attached. EQP-SI-05150 / EQP-CY-02354 (2021 SBC = 2019 A17.1 = 2023 NEC/SEC = 2020 A18.1) Status: Completed | Kone Inc (Primary) | $67K |
| applied Feb 10 | #7064376-CN Addition/Alteration · Building Construct alterations to minor telecommunications facility [AT&T] at rooftop level antenna and equipment room of warehouse storage building [RDA BUILDING] per plan. Status: Issued | Not published | $30K |
| applied Mar 19 | #7073760-CN Addition/Alteration · Building Demolition of existing tenant improvements in existing commercial building per plan. Work is related to # 7046835-CN Status: Issued | Not published | $373K |