Commercial General Building, Electrical work permitted April 3, 2025, with 6 permits through October 23, 2025, declaring $472,969 of work. Contractor on record: EZ Interface.
Grading for site improvements and asphalt play field at Martin Luther King Jr. ES per plan
Seattle permit records name EZ Interface, Dimensional Communications Inc. and Man Electric LLC as the contractors on this project, among 4 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
6 permits issued Apr 3 – Oct 23, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
Commercial and multifamily, biggest first.
#7113395-EL Electrical · Electrical Low Voltage Cabling Status: Completed |
| EZ Interface |
| $52K |
#7108349-EL Electrical · Electrical Install of IP Clocks (cable pull by others) Classroom AV Status: Completed | Dimensional Communications Inc. | $22.6K |
#7102641-EL Electrical · Electrical INSTALLATION OF NEW CCTV CAMERAS, ACCESS CONTROL, RECEPTACLES, AND AUDIO VISUAL SYSTEMS FOR THE ENTIRE SCHOOL OF MARTIN LUTHER KING JR ELEMENTARY. Status: Completed | Man Electric LLC | $100K |
#7098488-EL Electrical · Electrical 1 classroom AV shutdown, fire alarm relay ties to existing fire alarm system. Status: Completed | Red Hawk Fire Protection | $400 |
| applied Apr 14 | #7080689-CN Addition/Alteration · Building Install card readers and electric locks on non-egress sides of doors in institutional building (Martin Luther King Jr ES Brighton) subject to field inspection (STFI) Status: Completed | Not published | $48K |
| applied Apr 12 | #7007734-GR Grading · Grading Grading for site improvements and asphalt play field at Martin Luther King Jr. ES per plan Status: Completed | Not published | $250K |