Get ProEvery project in every city · from $79/mo
Get Procommercial project · Seattle, WA
Commercial General Building, Electrical work permitted February 13, 2025, with 3 permits through April 13, 2026, declaring $70,800 of work. Contractor on record: Prime Electric.
Get new commercial permits near 98108 or Seattle, free weekly email
Construct tenant improvements at manufacturing building (Orb Bottling Plant Ste270) on 2nd floor per plan.
Seattle permit records name Prime Electric as the contractor on this project.
3 permits issued Feb 13 – Apr 13, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
#7138082-EL Electrical · Electrical DB26035 - SKB Bottling Plant Panel Add- Job #1026269, Install new 200A feeder and 3-phase 120/208V 42-circuit panel fed from DP2. Includes conduit, metering device install, terminations. Includes (20) 20-1 Pole Breakers, 2nd Floor. Site Contact: Kevin Weber 4258903769 Status: Completed | Prime Electric |
Commercial and multifamily, biggest first.
| — |
| applied Dec 23 | #7114993-CN Addition/Alteration · Building Construct tenant improvements at manufacturing building (Orb Bottling Plant Ste270) on 2nd floor per plan. Status: Inspections Completed | Not published | $70K |
#7070408-EL Electrical · Electrical Replacing (1) exhaust fan JOB 1022228 Contact Jason Regis 425-213-3698 Status: Completed | Prime Electric | $800 |
In Seattle, biggest first.