Get ProEvery project in every city · from $79/mo
Get Promultifamily project · Seattle, WA
Multifamily Electrical, Elevator, Hvac/Mechanical work permitted April 3, 2025, with 6 permits through February 24, 2026, declaring $46,890 of work. Contractor on record: 16d LLC.
Elevator Cab Alterations Includes: Wall Panels, Handrails, Ceiling and Lights, Flooring, Cladding. EQP-SI-07041 / EQP-CY-05889 (2021 SBC=2019 A17.1=2023 NEC/SEC=2020 A18.1)
Seattle permit records name 16d LLC, Kirby Electric Incorporated and Vertical Dimensions as the contractors on this project.
Phone numbers and the property owner are included with Pro, where the city publishes them.
6 permits issued Apr 3 – Feb 24, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
Commercial and multifamily, biggest first.
#7130831-EL Electrical · Electrical Add 3-120v receptacles with USBC at setting counter Relocate 1-existing 120v receptacle for reefer Add 2-120v dedicated receptacles for new reefers Add 1-120v cord drop quad receptacle at worktables for mixers Add 1-S/P switch in unit 101 to control light fixtures Remove 7-existing chain hung… Status: Completed |
| Kirby Electric Incorporated |
| — |
#7110649-EL Electrical · Electrical Running a new circuit for compressor in adjacent room. Status: Completed | Not published | $500 |
| applied May 14 | #7078938-ME Mechanical · Trade For the purpose of elevator modernization: Install split unit in existing elevator machine room and adjacent parking garage Status: Completed | Not published | $9.6K |
| applied Apr 29 | #7082898-CY Conveyance · Trade Elevator Cab Alterations Includes: Wall Panels, Handrails, Ceiling and Lights, Flooring, Cladding. EQP-SI-07041 / EQP-CY-05889 (2021 SBC=2019 A17.1=2023 NEC/SEC=2020 A18.1) Status: Completed | Vertical Dimensions | $25.5K |
| applied Apr 4 | #7078946-RF Refrigeration · Trade For the purpose of elevator modernization: Refrigeration permit for 7078938-ME Status: Completed | 16d LLC | $9.6K |
#7078978-EL Electrical · Electrical ELECTRICAL FOR ELEVATOR MODERNIZATION Status: Completed | 16d LLC | $11.3K |
In Seattle, biggest first.