Multifamily General Building, Electrical work permitted September 24, 2025, with 3 permits through January 29, 2026, declaring $72,487 of work.
Scope is to install (20) EVSE fed from existing dedicated 600A EV Panel. [1/29/26 KEF - Plan set approved.]
Seattle’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
3 permits issued Sep 24 – Jan 29, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Jan 6 | #7123405-EL Electrical · Electrical Scope is to install (20) EVSE fed from existing dedicated 600A EV Panel. [1/29/26 KEF - Plan set approved.] Status: Completed | Not published | $52.5K |
Commercial and multifamily, biggest first.
#7125585-EL
Electrical · Electrical
Status: Issued
| Not published |
| — |
| applied Sep 22 | #7108049-CN Addition/Alteration · Building Repair in kind Unit 214 from fire damage subject to field inspection STFI. Status: Issued | Not published | $20K |