Get ProEvery project in every city · from $33/mo
Get Procommercial project · Buffalo, NY
Commercial General Building, Demolition work permitted December 24, 2024, with 6 permits through August 10, 2026, declaring $9,350,000 of work. Contractor on record: William Mahoney.
Buffalo Central Terminal Capital Improvements - Phase 2. Project to include interior renovation to a portion of the interior concourse and entry lobby finishes and MEP systems. Creation of a new exit stairwell, bathrooms, caterer kitchen and limited facade repairs. *** Digeplan *** *** Preservation *** *** Attached Asbestos Clearance *** *** BUFFALO CENTRAL TERMINAL TO MAKE PRESENTATION BEFORE LAND USE PLANNING BOARDS FALL 2026 *** *** All separate required mechanical, electrical and plumbing permits must be applied for as needed per permit. *** *** A separate DPW permit is required for any…
Buffalo permit records name William Mahoney, Christine Miller and Buffalo Construction Consultants as the contractors on this project.
Phone numbers and the property owner are included with Pro, where the city publishes them.
6 permits issued Dec 24 – Aug 10, newest first.
| Issued | Permit |
|---|
Commercial and multifamily, biggest first.
| Contractor |
|---|
| Value |
|---|
#GC26-9687676 GC · GENERAL CONTRACTOR Buffalo Central Terminal Capital Improvements - Phase 2. Project to include interior renovation to a portion of the interior concourse and entry lobby finishes and MEP systems. Creation of a new exit stairwell, bathrooms, caterer kitchen and limited facade repairs. *** Digeplan *** ***… | William Mahoney | $5M | |
#REP25-9668014 REP-PLANS · GENERAL CONTRACTOR Selective structural demolition of concrete slabs and concrete encasement of steel to allow for future repairs. *** Digeplan *** *** Asbestos Survey Attached *** | William Mahoney | $1.5M | |
#REP25-9634820 REP-PLANS · GENERAL CONTRACTOR Roofing Replacement. *** pos. survey attached - clearance letter due prior to final inspection *** ***Digeplan*** *** Pres. *** | William Mahoney | $1.5M | |
#REP25-9634818 REP-PLANS · GENERAL CONTRACTOR Resetting of stone balustrade pieces and masonry reconstruction of plaza masonry walls on a portion of the Southern and Western elevations. ***Digeplan*** | William Mahoney | $700K | |
#GC24-9626308 GC · GENERAL CONTRACTOR Installation of a new domestic water service connecting to a new valve and water main that the City of Buffalo Water installed in 2023 on Curtiss Street. Work includes a new water service room within the building including new lighting, power outlets, and electric unit heater. *** SEPARATE… | Christine Miller | $150K | |
#TEAR24-9627224 TEAROUT Asbestos abatement and selective demolition within the Buffalo Central Terminal to allow for future renovation work to occur. *** CLEAN LETTER DUE PRIOR TO PERMIT FINAL *** *** POS. SURVEY IN DIGEPLAN *** | Buffalo Construction Consultants | $2M |