Commercial General Building, Electrical, Fire Protection, Hvac/Mechanical, Plumbing work permitted October 22, 2025, with 6 permits through September 14, 2026, declaring $11,179,921 of work. Contractor on record: Industrial Power And Lighting Corp.
Pre-Engineered Building addition to an existing manufacturing facility: New F-1 Occupancy: 38,857 sf New B Occupancy: 5,509 sf. *** DIGEPLAN*** ***PLANS FILED*** ***MINOR SITE*** ***CURB CUT***
Buffalo permit records name Industrial Power And Lighting Corp, Anthony Hertel Hardware & Plumbing and Timothy Perkins as the contractors on this project, among 6 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
6 permits issued Oct 22 – Sep 14, newest first.
Commercial and multifamily, biggest first.
| Issued | Permit | Contractor | Value |
|---|
#ELEC26-9706477 ELECTRICAL · MASTER ELECTRICIAN Provide new electrical service to the existing building and building addition. Provide electrical build out of the addition which includes the construction of a new office area and new production space. The electrical work will consist of: branch electrical panels, receptacles, lighting, lighting… | Industrial Power And Lighting Corp | $1.7M | |
#PLUM26-9701864 PLUMBING · PLUMBERS MASTER ROUGH IN AND FINISH 2 RESTROOMS (5 WATERCLOSETS,1 URINAL, 4 LAV SINKS) 1 DRINKING FOUNTAIN 1 MOP SINK 1 KITCHEN SINK | Anthony Hertel Hardware & Plumbing | $245K | |
#REP26-9692029 REP-PLANS · SPECIALTY CONTRACTOR Install new fire sprinkler system and run new bulk main to feed existing systems. *** Digeplan *** | Timothy Perkins | $165K | |
#GC25-9661012 GC · GENERAL CONTRACTOR Pre-Engineered Building addition to an existing manufacturing facility: New F-1 Occupancy: 38,857 sf New B Occupancy: 5,509 sf. *** DIGEPLAN*** ***PLANS FILED*** ***MINOR SITE*** ***CURB CUT*** | William Mahoney | $8M | |
#HEAT26-9682309 HEATING · HEATING CONTRACTOR Installation of RTUs, MUAs, ductless split system HP, fans, wall heater, associated RGDs and ductwork as per spec'd plan | Robin Cloy | $293K | |
#REP25-9664088 REPAIR · HOME IMPROVEMENT CONTRACTOR To an existing commercial block building reroof with new .060SAT IPO FULLY ADHERED ROOF SYSTEM. | William J Sahlem | $777K |