Multifamily General Building, Demolition, Fire Protection, Hvac/Mechanical, Plumbing, Sign work permitted November 6, 2024, with 12 permits through February 27, 2026, declaring $64,510,100 of work.
Site development for onsite improvments related to new Mercy Aviva Crossing Apartment Building including private streets, courtyard areas, and utility improvements. Field Revision 1: FRC26-0002 Approved 3.11.26:" The play area in the north courtyard has been changed to rubberized safety tiles, with the grading and drainage revised accordingly. Related to SDEV23-0432. ***FRC26-0078 APPROVED 03/31/26 Description of change: Revised curb return at southeast corner to 15’ due to conflicts between curbs and utility vaults. The fire truck and garbage truck drawings are vehicle turn models provided…
Tacoma’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
12 permits issued Nov 6 – Feb 27, newest first.
| Issued | Permit | Contractor | Value |
|---|
Commercial and multifamily, biggest first.
| applied Feb 6 | #SIGN26-0012 Sign Install a single faced non illuminated Monument sign at Aviva Crossing Status: Finaled | Not published | $4.4K |
| applied Jul 31 | #FIREC25-0174 Building · Fire Protection Install SMOKE CONTROL Elevator Pressurization System and Exhaust for Garage Provide Integration with Building, Mechanical, Electrical And Fire Protection. at MULTI FAM HIGH RISE 5 UNITS OR MORE Status: Finaled | Not published | $1.8M |
| applied Nov 14 | #FIREC25-0278 Building · Fire Protection Low voltage installation of ERCES/DAS, less conduit and cable at Mercy Housing Avia Crossing. Status: Permit Issued | Not published | $30.3K |
| applied Jun 26 | #FIREC25-0138 Building · Fire Protection Install a Fire Alarm System. Status: Finaled | Not published | $75K |
| applied Jun 6 | #WO25-0076 Site This project upgrades an existing RRFB on S Mildred St to meet current city standards. Status: Final Inspection | Not published | — |
| applied Feb 11 | #FIREC25-0031 Building · Fire Protection Installation of Wet and Dry Fire Sprinklers, and Fire Pump. Status: Finaled | Not published | $611K |
| applied Mar 5 | #FIREC25-0044 Building · Fire Protection Installation of underground fire protection water supply from city meter to flange inside building. Status: Permit Issued | Not published | $5K |
| applied Dec 13 | #PLMBC24-0256 Building · Plumbing PLUMBING FOR A NEW FIVE-STORY SINGLE-USE BUILDING WITH FOUR STORIES OF R-2 RESIDENTIAL ABOVE A ONE-STORY STRUCTURED PARKING GARAGE. Status: Finaled | Not published | $3.2M |
| applied Sep 4 | #MECHC24-0230 Building · Mechanical Corridor ventilation system via packaged heat pump rooftop units, garage exhaust, common space heating & cooling via high efficiency heat pumps, ventilation via ERV's, trash room exhaust, residential unit venting ERVs. Status: Finaled | Not published | $562K |
| applied Jan 9 | #BLDCN23-0094 Building · New Building Construction of a five (5) story, 129 unit VA construction Multi-family Apartment Building. Related to: MECHC24-0230 ***FRC25-0109 APPROVED 05/08/25 Structural and architectural revisions*** *** FRC26-0034 - Approved - 03/05/2026 - Revised the location of the type A units and the units with… Status: Finaled | Not published | $23.2M |
| applied Dec 22 | #SDEV23-0432 Site Site development for onsite improvments related to new Mercy Aviva Crossing Apartment Building including private streets, courtyard areas, and utility improvements. Field Revision 1: FRC26-0002 Approved 3.11.26:" The play area in the north courtyard has been changed to rubberized safety tiles,… Status: Finaled | Not published | $35M |
| applied Aug 13 | #DEMOC24-0013 Building · Demolition Demolition of existing 1-story building, approximately 3,600sf. and covered entryway down to foundation. Status: Finaled | Not published | $45K |