Get ProEvery project in every city · from $79/mo
Get Procommercial project · Seattle, WA
Commercial General Building, Electrical, Fire Protection work permitted March 31, 2025, with 11 permits through August 6, 2026, declaring $457,741 of work. Contractor on record: JH Kelly, LLC.
Grading improvements to remove and replace pavement at institution property (North Seattle College) per plan.
Seattle permit records name JH Kelly, LLC, Columbia Fire and Datskiy Electric LLC as the contractors on this project, among 7 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
11 permits issued Mar 31 – Aug 6, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
Commercial and multifamily, biggest first.
| applied Jul 27 |
#7154963-EL Electrical · Electrical Replace 4 like for like panels and breakers, all breakers and panels are replacing existing breakers and panels with amperage and voltage. [*7-27-29 D Rankin - we need photos of the existing, fault current available at the panels and for the new, information on the new products, i.e. panel… Status: Completed |
| JH Kelly, LLC |
| $30K |
#7128469-FS Fire Sprinkler and Suppression · Trade Removing 2 heads Status: Completed | Columbia Fire | $2K |
| applied Jan 7 | #7117092-CN Addition/Alteration · Building Construct alterations for child care restroom first floor north end of existing institutional building per plan. Mechanical included. Status: Issued | Not published | $10.8K |
| applied Dec 18 | #7121902-EL Electrical · Electrical Gut MCC cabinet control contactors and utilize existing fused switch as a disconnect Build Strut rack to hold 2 new VFD's Use basement of MCC as race way and existing raceway to the motor(s). Status: Completed | JH Kelly, LLC | $20K |
#7120091-EL Electrical · Electrical Electrical like for like replacement. Status: Completed | Datskiy Electric LLC | $6K |
#7117986-EL Electrical · Electrical Requesting Consultation - To approve means of disconnect. Status: Completed | JH Kelly, LLC | $1K |
#7086189-EL Electrical · Electrical Installation of (1) 200a. 480v. 3 phase Temporary generator. Status: Completed | Milne Electric | $3.3K |
#7085831-EL Electrical · Electrical Job 524747- 500kw generator with temp cord routing to (1) 800-amp temp panel with a (1) 400-amp & (1) 200-amp circuit breaker. Status: Completed | Cochran Inc. | $35K |
| applied Sep 16 | #7034863-GR Grading · Grading Grading improvements to remove and replace pavement at institution property (North Seattle College) per plan. Status: Completed | Not published | $300K |
#7080867-EL Electrical · Electrical Relocate existing surface receptacles into new framed walls, no load change and demo some old electrical lighting. JOB 1022879 Contact Mike Kinney 425-429-4654 Status: Completed | Prime Electric | $7.6K |
#7078148-EL Electrical · Electrical DDC Upgrade Job 836083 [5/21/2025 PGF Added (5) 15A dedicated appliance circuits to permit for power monitoring systems per contractor request (Breanne). Post-issuance change fee included.] Status: Completed | EC Electric | $42K |
In Seattle, biggest first.