Commercial General Building, Electrical, Fire Protection, Hvac/Mechanical work permitted July 23, 2025, with 7 permits through September 9, 2025, declaring $391,429 of work. Contractor on record: Tempest Technologies.
Construct tenant improvements for existing offices on third floor occupy per plan.
Seattle permit records name Tempest Technologies, Johnson Controls Fire Protection and OEG, Inc as the contractors on this project, among 4 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
7 permits issued Jul 23 – Sep 9, newest first.
| Issued | Permit | Contractor | Value |
|---|
Commercial and multifamily, biggest first.
#7105795-EL Electrical · Electrical INSTALLATION OF LOW VOLTAGE AUDIO VIDEO CONFERENCING SYSTEMS IN ROOMS 303, 302 AND 301. Status: Completed | Tempest Technologies | $54K | |
| applied Aug 4 | #7099813-EL Electrical · Electrical Install new fire alarm system the O'Shea Building (1524 5th Ave) Suite 300. Install (29 new devices). Joint venture between John Controls Fire Protection (JOHNSCP831PR) and Pride Electric Inc. (OEG*II*823NF). Status: Completed | Johnson Controls Fire Protection | $13.9K |
| applied Jul 23 | #7097398-FS Fire Sprinkler and Suppression · Trade 23 head sprinkler tenant improvement. Heads to be added / relocated for new wall and ceiling layout. Status: Completed | Not published | $11.5K |
#7101722-EL Electrical · Electrical Installation of Data locations Status: Completed | Not published | $3.5K | |
#7101334-EL Electrical · Electrical Tenant improvement using existing circuits. JOB#438343 Status: Completed | OEG, Inc | $40.3K | |
| applied Jul 31 | #7099113-ME Mechanical · Trade OOKLA TI - Provide and install two new EF's and perform misc. duct and GRD mods - Subject to Field Inspection (STFI) Status: Completed | Enviromech | $18.2K |
| applied May 19 | #7077014-CN Addition/Alteration · Building Construct tenant improvements for existing offices on third floor occupy per plan. Status: Completed | Not published | $250K |