Commercial General Building, Electrical, Elevator, Hvac/Mechanical work permitted March 31, 2025, with 11 permits through July 17, 2026, declaring $153,296 of work. Contractor on record: Macdonald Miller Facility Solutions LLC.
Boiler #2: we replaced the old Honeywell burner controls on the gas and oil systems. We also recommissioned both systems
Seattle permit records name Macdonald Miller Facility Solutions LLC, Chinook Elevator Solutions LLC and Artline as the contractors on this project, among 4 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
11 permits issued Mar 31 – Jul 17, newest first.
| Issued | Permit | Contractor |
|---|
Commercial and multifamily, biggest first.
| Value |
|---|
#7153606-EL Electrical · Electrical 42223 PERFORM GENERATOR LOAD BANK Status: Completed | Not published | — | |
#7130571-BP Boiler/Pressure Vessel · Trade Demo and remove the Armstrong AX-144 expansion tank ? Provide and install the following: o B&G B300 non-potable water ASME tank o 80-gallon, o 125 PSI, 240ºF rated o Butyl bladder type 40 PSI pre-charge, 1.5" connection Status: Completed | Macdonald Miller Facility Solutions LLC | $8.8K | |
| applied May 19 | #7076605-CN Addition/Alteration · Building Construct alterations to modify existing Minor Communication Utility [VERIZON] at roof of existing apartment building per plan. Status: Completed | Not published | $21K |
#7120482-BP Boiler/Pressure Vessel · Trade Boiler #2: we replaced the old Honeywell burner controls on the gas and oil systems. We also recommissioned both systems Status: Completed | Macdonald Miller Facility Solutions LLC | $45.3K | |
#7120485-BP Boiler/Pressure Vessel · Trade Boiler #1: we replaced the old Honeywell burner controls on the gas and oil systems. We also recommissioned both systems Status: Completed | Macdonald Miller Facility Solutions LLC | $45.3K | |
#7114022-EL Electrical · Electrical Install new Boiler in Replacement of old. Status: Issued | Macdonald Miller Facility Solutions LLC | $5.5K | |
| applied Oct 23 | #7113117-CY Conveyance · Trade Install LVT Flooring. 115 lbs in/ 115 lbs out - Car #1 EQP-SI-07646 / EQP-CY-06474 (2021 SBC = 2019 A17.1 = 2023 NEC/SEC = 2020 A18.1) Status: Completed | Chinook Elevator Solutions LLC | $27K |
| applied Oct 23 | #7113123-CY Conveyance · Trade Install LVT Flooring. Weight in 115 lbs/ Weight out 115 lbs - Car #2 EQP-SI-07646 / EQP-CY-06475 (2021 SBC = 2019 A17.1 = 2023 NEC/SEC = 2020 A18.1) Status: Completed | Chinook Elevator Solutions LLC | $27K |
#7091921-EL Electrical · Electrical Installing 21 Cat 6 cables for AP. Installing J-hooks for pathway. Installing backboard, rack, equipment, & patch panels. All voice and data low voltage cabling. Status: Completed | Clearnet Communications | $15.5K | |
| applied May 14 | #7085741-CY Conveyance · Trade install glide P door operator - Elev. 2 EQP-SI-07646 / EQP-CY-06475 (2021 SBC = 2019 A17.1 = 2023 NEC/SEC = 2020 A18.1) Status: Completed | Artline | $30.2K |
| applied Mar 31 | #7077977-CY Conveyance · Trade install glide A door operator EQP-SI-07646 / EQP-CY-06474 (2018 SBC = 2020 SEC = 2019 A17.1 = 2017 A18.1) Status: Completed | Artline | $30.2K |