Multifamily Electrical work permitted February 26, 2025, with 4 permits through March 4, 2026, declaring $72,793 of work. Contractor on record: Nelson Electric Incorporated.
Scope is to install new 112.5KVA XFMR and 250A panel feeding 20 WallBox EVSE in stalls 27-46 and future infrastructure in stalls 24-26.
Seattle permit records name Nelson Electric Incorporated as the contractor on this project.
Phone numbers and the property owner are included with Pro, where the city publishes them.
4 permits issued Feb 26 – Mar 4, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Mar 3 | #7131510-EL Electrical · Electrical Scope is to install new 112.5KVA XFMR and 250A panel feeding 20 WallBox EVSE in stalls 27-46 and future infrastructure in stalls 24-26. Status: Completed | Not published | $62.8K |
Commercial and multifamily, biggest first.
#7094811-EL Electrical · Electrical 77098 - Coppins Well, add heater in fire pump room.[7/8/2025 JBC Added 60amp Feeder to Permit] Status: Completed | Nelson Electric Incorporated | $2.5K |
| applied Mar 5 | #7073675-EL Electrical · Electrical 75429 - Coppins well fire pump controller replacement. Existing fire pump controller has failed. Disconnect power to fire pump controller and reconnect power to like for like replacement. Fire pump controller provided and installed by others. Status: Completed | Nelson Electric Incorporated | $7.5K |
#7072482-EL Electrical · Electrical 75429 - Coppins well fire pump controller replacement. Existing fire pump controller has failed. Disconnect power to fire pump controller and reconnect power to like for like replacement. Fire pump controller provided and installed by others. [C.Kenefick 3/14/2025 - this is now FA permit, 6… Status: Completed | Nelson Electric Incorporated | $7.5K |
In Seattle, biggest first.