Get Procommercial project · Nashville, TN
Commercial General Building, Sign work permitted November 4, 2024, with 6 permits through September 15, 2026, declaring $59,280,000 of work.
to conduct renovations to floors 4-6 & 8-11 and convert to hotel use. no change to footprint. bb poc jeff walters
Nashville’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
6 permits issued Nov 4 – Sep 15, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Jun 26 | #2026053707 Building Commercial - Rehab To conduct interior renovations for SONGTELLER HOTEL. To include interior demolition and build/finish-out of 7th floor to covert to new guestroom space for hotel occupancy expansion. No change to exterior building/roof lines or footprint. DTC, MDHA-CM, OV-UZO. | Not published | $4M |
Commercial and multifamily, biggest first.
#2025072709 Building Commercial - Amend Permit To amend scope of work permitted under CACR-2024037237 for interior demolition within existing commercial building. Amended work to include additional interior demolition located on 7th floor only. No change to exterior building/roof lines or footprint. Poc: Jeff Walters 865-755-9467… |
| Not published |
| $150K |
| applied Oct 22 | #2025089179 Building Sign Permit To erect/replace 1 illuminated legally non-conforming skyline sign & to erect 1 new illuminated skyline sign for Dolly Parton’s Song Teller Hotel. Existing skyline sign legally non-conforming under original sign permit #200919862. Zoning Administrator approved proposed skyline sign under the… | Not published | $130K |
| applied Jan 15 | #2025003581 Building Commercial - Addition to conduct ph 3 renovations to existing building including enclosing of a breezeway as well as the addition to the building to accommodate new elevator. not to be over any easements. bb poc jeff walters | Not published | $4M |
| applied Nov 20 | #2024103881 Building Commercial - Rehab The project is the conversion of an existing 12-story high-rise office building into a uniquely branded hotel. The existing building includes 5-level subterranean public parking garage that is not in scope. This is for Phase 2 of construction. Phase 2 consists/includes the Public Space Components… | Not published | $10M |
| applied Jul 8 | #2024062066 Building Commercial - Rehab to conduct renovations to floors 4-6 & 8-11 and convert to hotel use. no change to footprint. bb poc jeff walters | Not published | $45M |