How long commercial permits take in Nashville, by trade
Median days from application to issue and median declared value, commercial and multifamily permits issued July 31, 2026 – October 29, 2026.
| Trade | Permits | Median days to issue | Median declared value |
|---|---|---|---|
| Building | 1,057 | 70 | $201K |
| Signs | 91 | 10 | $2.5K |
| Demolition | 22 | 20 | $34.1K |
| Roofing | 17 | 14 | $155K |
Counts only permits whose record includes an application date (1,187 of 1,187). Times depend on the city’s review track: express and over-the-counter trade permits often issue within days, new construction takes longer.