Commercial General Building work permitted July 14, 2025, with 2 permits through May 5, 2026, declaring $1,905,666 of work. Contractor on record: Abbot Building Restoration.
Cut and point masonry joints 100%. Replace select deteriorated stone elements. Coat all stone elements to match existing. Cut out and recaulk all windows in kind. Paint window trim in kind.
Cambridge permit records name Abbot Building Restoration as the contractor on this project.
Phone numbers and the property owner are included with Pro, where the city publishes them.
2 permits issued Jul 14 – May 5, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Apr 29 | #1208881 Building: Alteration and Addition Phase 2: REAR ELEVATIONS: Cut and point masonry joints 100%. Replace select deteriorated stone elements. Coat all stone elements in kind. Cut out and recaulk all windows. Paint window trim and fire escapes. Status: Active |
Commercial and multifamily, biggest first.
| Abbot Building Restoration |
| $830K |
| applied Jun 23 | #1171134 Building: Alteration and Addition Cut and point masonry joints 100%. Replace select deteriorated stone elements. Coat all stone elements to match existing. Cut out and recaulk all windows in kind. Paint window trim in kind. Status: Complete | Abbot Building Restoration | $1.1M |
In Cambridge, biggest first.