Commercial General Building, Fire Protection, Hvac/Mechanical, Plumbing work permitted December 27, 2024, with 9 permits through May 18, 2026, declaring $192,626 of work.
Get new commercial permits near 98403 or Tacoma, free weekly email
Install VRF system to heat/cool new fitness rooms. Install DOAS units to ventilate new fitness rooms and bathrooms. Install two exhaust fans in existing mechanical room.
Tacoma’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
9 permits issued Dec 27 – May 18, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Apr 24 | #FIREC26-0076 Building · Fire Protection Re-piping over a 10 burner range on a Ansul R-102 system for proper coverage Status: Permit Issued |
Commercial and multifamily, biggest first.
| $6K |
| applied Aug 6 | #FIREC25-0178 Building · Fire Protection For the purpose of elevator modernization: Relocate existing elevator machine room detector. Install relays for recall and hat light Status: Finaled | Not published | $2.2K |
| applied Jun 30 | #MECHC25-0172 Building · Mechanical For the purpose of elevator modernization: Install split unit in existing elevator machine room and nearby storage/mechanical space Status: Finaled | Not published | $9.6K |
| applied Jun 25 | #MECHC25-0166 Building · Mechanical Replace above ceiling in line exhaust fan in girls bathroom. Connect to existing ductwork. at : ELEM SCHOOLS 1 TO 6 Status: Finaled | Not published | $3K |
| applied Jun 25 | #PLMBC25-0180 Building · Plumbing Replacing 2 toilets, 2 sinks, and 1 hose bib. Status: Finaled | Not published | $10K |
| applied Jan 30 | #BLDCA25-0035 Building · Alteration Reconstruct two walls for removal and reinstallation of elevator pump unit. Status: Finaled | Not published | $15K |
| applied Apr 14 | #STORM25-0011 Utility Connection Repair stormwater connection for school building. No ROW. Status: Permit Issued | Not published | $1K |
| applied Sep 20 | #MECHC24-0248 Building · Mechanical Install VRF system to heat/cool new fitness rooms. Install DOAS units to ventilate new fitness rooms and bathrooms. Install two exhaust fans in existing mechanical room. Status: Finaled | Not published | $125K |
| applied Nov 1 | #FIREC24-0251 Building · Fire Protection Extending existing fire sprinkler system coverage into new fitness area and bathrooms at ELEM SCHOOLS 1 TO 6 Status: Finaled | Not published | $20.8K |