Commercial General Building work permitted May 4, 2026, with 4 permits through August 10, 2026, declaring $1,290,000 of work.
Onsite Improvements: Conversion of the existing grass field to synthetic turf at Birney Elementary School. ***FRC26-0212 - APPROVED - 08/06/2026 - Conversion of the existing grass field to synthetic turf at Birney Elementary School. FRC pertains to WO25-0145, trees added to field parcel.***
Tacoma’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
4 permits issued May 4 – Aug 10, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Jun 17 | #STORM26-0026 Utility Connection New stormwater connection related to conversion of the existing grass field to synthetic turf Status: Finaled | Not published | — |
Commercial and multifamily, biggest first.
#WO25-0145 Site Replacement of sidewalk on east side of South Sheridan Ave. Status: Permit Issued |
| Not published |
| $70K |
| applied Dec 22 | #SDEV25-0402 Site Onsite Improvements: Conversion of the existing grass field to synthetic turf at Birney Elementary School. ***FRC26-0212 - APPROVED - 08/06/2026 - Conversion of the existing grass field to synthetic turf at Birney Elementary School. FRC pertains to WO25-0145, trees added to field parcel.*** Status: Permit Issued | Not published | $1.2M |
| applied Feb 19 | #BLDCA26-0046 Building · Alteration Install 15' high chain link fence backstop at Birney Elementary School. Status: Permit Issued | Not published | $20K |