Get Procommercial project · Tacoma, WA
Commercial General Building, Plumbing work permitted February 5, 2025, with 5 permits through September 26, 2025, declaring $150,000 of work.
Install of solar mounting 105 Q.peak Duo XL-G.10.3/BFG 485W(50.92 kwdc stc/ 50.400 kw ac rooftop ballasted PV system.
Tacoma’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
5 permits issued Feb 5 – Sep 26, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Dec 6 | #BLDCA24-0462 Building · Alteration Install of solar mounting 105 Q.peak Duo XL-G.10.3/BFG 485W(50.92 kwdc stc/ 50.400 kw ac rooftop ballasted PV system. Status: Permit Issued | Not published | $150K |
Commercial and multifamily, biggest first.
#WATER25-0014 Utility Connection WATER CONNECTION FOR BUILDING B ASSOCIATED PERMIT SDEV22-0365 Status: Finaled |
| Not published |
| — |
| applied Feb 3 | #WATER25-0015 Utility Connection NEW WATER LINE SERVICE FOR BUILDING A MULTI FAM APTS 5 UNITS OR MORE ASSOCIATED PERMIT SDEV22-0365 Status: Finaled | Not published | — |
| applied Feb 3 | #SEWER25-0079 Utility Connection SEWER CONNECTION PERMIT FOR MULTIFAMILY DEVELOPMENT Status: Finaled | Not published | — |
| applied Feb 3 | #STORM25-0003 Utility Connection SURFACE WATER CONNECTION FOR MULTIFAMILY DEVELOPMENT Status: Finaled | Not published | — |