Get ProEvery project in every city · from $79/mo
Get Promultifamily project · Tacoma, WA
Multifamily General Building, Fire Protection, Hvac/Mechanical, Plumbing work permitted March 5, 2025, with 9 permits through February 25, 2026, declaring $1,515,415 of work.
Develop and Build a 6 unit apartment building. Associated with BLDCN23-0029 and SDEV23-0420
Tacoma’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
9 permits issued Mar 5 – Feb 25, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Nov 17 | #FIREC25-0281 Building · Fire Protection Install FACP to monitor sprinkler system (installed by others) at South C Street Apts Status: Finaled | Not published | $4.7K |
Commercial and multifamily, biggest first.
| applied Jan 8 | #WATER26-0003 Utility Connection New water lines at apartment building. Status: Finaled | Not published | $200 |
| applied Jan 8 | #STORM26-0001 Utility Connection New stormwater connection for apartment building **APPROVED UNDER WO24-0057** Status: Finaled | Not published | $100 |
| applied Apr 26 | #WO24-0057 Site Develop and Build a 6 unit apartment building. Associated with BLDCN23-0029 and SDEV23-0420 Status: Closed | Not published | $750K |
| applied Apr 29 | #FIREC25-0088 Building · Fire Protection Fire Sprinkler System Status: Finaled | Not published | $29.4K |
| applied Jun 12 | #PLMBC23-0155 Building · Plumbing Plumbing for new 6-unit multifamily building Status: Finaled | Not published | $30K |
| applied Dec 19 | #SEWER24-0914 Utility Connection New open trench of the sanitary sewer for future 6 unit multifamily building. Alley/gravel will be paved over as part of restoration Status: Finaled | Not published | $1K |
| applied Jun 12 | #MECHC23-0185 Building · Mechanical Mechanical for new 6-unit multifamily building Status: Finaled | Not published | $30K |
| applied Dec 6 | #SDEV23-0420 Site Onsite improvements associated with the construction of a 6 unit apartment building. Related to BLDCN23-0029. ***FRC26-0058 APPROVED 07/24/26 AS BUILT*** Status: Finaled | Not published | $700K |