Commercial General Building, Electrical, Fire Protection, Hvac/Mechanical work permitted January 17, 2025, with 36 permits through October 27, 2026, declaring $973,629 of work. Contractor on record: ACCO Engineered Systems.
Construct tenant improvement in existing office building at level 7 per plan.
Seattle permit records name ACCO Engineered Systems, Holaday Parks Inc and OEG, Inc as the contractors on this project, among 8 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
The contractor on 1 permit issued in the last 30 days is included with Pro.
See the contractorCommercial and multifamily, biggest first.
In Seattle, biggest first.
36 permits issued Jan 17 – Oct 27, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
#7169378-EL Electrical · Electrical Low voltage controls for 1 VAV 12th Floor. Status: Issued | Contractor with Pro | — | |
#7150165-EL Electrical · Electrical Low voltage - installation of controls for 1 heat pump. 12th floor Status: Completed | Holaday Parks Inc | — | |
#7143357-EL Electrical · Electrical Relocate (1) thermostat Status: Issued | ACCO Engineered Systems | — | |
#7141317-EL Electrical · Electrical Replacing access control and video surveillance system Status: Completed | Convergint | — | |
#7132667-EL Electrical · Electrical LV Energy Management, 3 Devices, One per Floor. 7th, 12th, 22nd Status: Completed | Holaday Parks Inc | — | |
#7126856-EL Electrical · Electrical Status: Completed | OEG, Inc | — | |
#7124306-EL Electrical · Electrical Low Voltage Energy Management, 1 Device. Replace 1 Controller. 8th Floor Status: Completed | Holaday Parks Inc | — | |
#7124038-EL Electrical · Electrical Status: Issued | Not published | — | |
| applied Dec 2 | #7119155-EL Electrical · Electrical Joint venture between Convergint and Pride Electric. Relocation of 4 speaker strobes, installation of 5 speaker only and 1 speaker strobe devices. Status: Completed | Not published | $225 |
#7119659-EL Electrical · Electrical Pull 33 single cat 6 drops and 15 dual cat 6a drops Status: Completed | Kao electric LLC | $2K | |
#7119349-EL Electrical · Electrical Tenant Improvement using existing circuits. JOB#439470 [C.Kenefick 1/12/2026 - fee for exit signs and hvac added to permit.] Status: Completed | OEG, Inc | $24.4K | |
| applied Nov 24 | #7118006-ME Mechanical · Trade 1. Relocate (1) VAV box; 2. Add (1) New VAV box with Electric Heat; 3. Grilles, ducts, and diffusers per plan. Status: Completed | ACCO Engineered Systems | $21.6K |
| applied Nov 13 | #7116282-ME Mechanical · Trade Provide and install HVAC system, per plan Status: Completed | ACCO Engineered Systems | $36K |
#7115711-EL Electrical · Electrical LV Energy Management, 1 Device Status: Completed | Holaday Parks Inc | $2K | |
#7115060-EL Electrical · Electrical Low Voltage permit for 4 t-stats Status: Issued | ACCO Engineered Systems | $1K | |
#7112482-EL Electrical · Electrical We are installing (1) speaker/strobe as a joint venture with Titan Electric. Status: Completed | Not published | $7.1K | |
#7111802-EL Electrical · Electrical Install 3 Switches Install 7 Outlets Install 1 Exit Sign Job#:2501610 Status: Completed | Titan Electric Inc | $18K | |
#7110655-FS Fire Sprinkler and Suppression · Trade 8 Head TI job for new wall and ceiling layout. Status: Completed | Not published | $3K | |
#7107063-EL Electrical · Electrical LV Energy Management, 1 device. Replace bad controller. Status: Completed | Holaday Parks Inc | $2K | |
#7104047-EL Electrical · Electrical Low voltage permit for T-stats Status: Completed | ACCO Engineered Systems | $500 | |
#7103650-EL Electrical · Electrical PERFORM GENERATOR LOAD BANK; [9/28/26 RN Renewal/Reinstatement fee added] Status: Issued | Not published | $500 | |
| applied Aug 19 | #7101712-ME Mechanical · Trade Relocate grilles and diffusers - Subject to Field Inspection (STFI) Status: Completed | ACCO Engineered Systems | $2.5K |
#7102301-EL Electrical · Electrical 435065 Puckett & Redford, Suite 800 low voltage data cabling. Status: Completed | OEG, Inc | $6.2K | |
#7099837-EL Electrical · Electrical Tenant improvement using existing circuits. JOB # 437777 Status: Completed | Pride Electric, Inc | $6.3K | |
#7094840-EL Electrical · Electrical Tenant improvement using existing panel board and circuits. JOB#437777 Status: Completed | Pride Electric, Inc | $8.3K | |
| applied Jun 23 | #7092687-CN Addition/Alteration · Building Construct tenant improvement for office space at level 8 of existing commercial building subject to field inspection (STFI) Status: Completed | Not published | $113K |
#7076001-EL Electrical · Electrical Pitchbook-114033738-08 Johnson Controls (JCI) is to install new door release buttons into the existing Brivo Access Control Panel at PitchBook facilities located at 901 5th Ave, Seattle, WA, 98164. JCI will program and install the following field devices: Field Devices: - Two (2) Door Release… Status: Completed | Not published | $3.1K | |
| applied Jan 31 | #7068207-FS Fire Sprinkler and Suppression · Trade 32 heads. Tenant Improvement for new wall and ceiling layout. Status: Completed | Not published | $13.5K |
| applied Feb 4 | #7068745-EL Electrical · Electrical Tenant improvement for the 7th floor of 901 5th for PitchBook.. We have assumed new and reuse of existing ceiling mount notification devices. Devices include speaker/strobes, strobes, and speakers. Visual notification has been provided within all public areas, break rooms, conference rooms, and… Status: Completed | Convergint Technologies | $13K |
| applied Feb 10 | #7069193-EL Electrical · Electrical 7th Floor TI using existing panel boards, load centers, and circuits. Status: Completed | Pride Electric, Inc | $215K |
| applied Dec 10 | #7046556-CN Addition/Alteration · Building Construct tenant improvement in existing office building at level 7 per plan. Status: Completed | Not published | $424K |
#7069953-EL Electrical · Electrical 436581 GATEWAY PITCHBOOK FLOOR 7 - GET STARTED PERMIT FOR PERMIT 7069193-EL. Status: Completed | OEG, Inc | $8K | |
#7067590-EL Electrical · Electrical 01-411032 PERFORM 2 HOUR LOAD BANK TEST ON STANDBY GENERATOR ONLY. DISCONNECT BUILDING CONDUCTORS, CONNECT LOAD BANK, PERFORM LOAD BANK TEST, LAND AND TORQUE ORIGINAL BUILDING CONDUCTORS. Status: Completed | Not published | $2.1K | |
#7066824-EL Electrical · Electrical 435033 Low voltage data cabling Status: Completed | OEG, Inc | $17.1K | |
| applied Jan 6 | #7062820-ME Mechanical · Trade Relocate and add VAVs as necessary to support TI floor plan. Status: Completed | ACCO Engineered Systems | $28K |
#7065863-EL Electrical · Electrical LV Energy Management, 3 Devices. 7th Floor Status: Completed | Holaday Parks Inc | $2K |