Commercial Electrical, Hvac/Mechanical work permitted November 24, 2025, with 5 permits through August 31, 2026, declaring $104,700 of work. Contractor on record: McKinstry Co LLC.
Replacement of a failed chiller for process cooling. Relocating from the current space inside to the outside. Piping chilled water lines to the new location and rerouting the electrical circuit to the new location.
Seattle permit records name McKinstry Co LLC, Washington Alarm Inc and FlyLock Security Solutions Seattle as the contractors on this project, among 4 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
5 permits issued Nov 24 – Aug 31, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
Commercial and multifamily, biggest first.
#7160519-EL Electrical · Electrical Installation of a new Security System. Status: Completed |
| Washington Alarm Inc |
| — |
#7156455-EL Electrical · Electrical Installing a 4-door card reader access control system to the building. Installing card readers, electrified locks, and 1 control enclosure. Status: Issued | FlyLock Security Solutions Seattle | — |
#7144689-EL Electrical · Electrical Adding 1-100amp 480 volt circuit and modifying existing control solenoids. Status: Completed | McKinstry Co LLC | — |
| applied Feb 5 | #7120374-ME Mechanical · Trade Replacement of a failed chiller for process cooling. Relocating from the current space inside to the outside. Piping chilled water lines to the new location and rerouting the electrical circuit to the new location. Status: Issued | McKinstry Co LLC | $89.7K |
#7118317-EL Electrical · Electrical Install CAT6 Wiring for IP Camera System Status: Completed | Pacific Business Systems, Inc. | $15K |