Get ProEvery project in every city · from $79/mo
Get Procommercial project · San Francisco, CA
Commercial General Building work permitted August 22, 2025, with 6 permits through September 16, 2026, declaring $3,290,000 of work. Contractor on record: B N Builders Inc.
3/f, 4/f, 5/f - partial demo of non structural walls, ceilings and light fixtures. new construction of non structural walls, finishes and power. mech and electr included.
San Francisco permit records name B N Builders Inc, Sc Builders, Inc and Skyline Construction as the contractors on this project.
Phone numbers and the property owner are included with Pro, where the city publishes them.
6 permits issued Aug 22 – Sep 16, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Aug 31 | #202608317428 |
Commercial and multifamily, biggest first.
otc alterations permit
5/f: selective demo and construction of non-load bearing partitions, (e) mods to ceiling grid & tile, light ficture relocatoi and new inlcuding reswitching, new doors & frames, millwork and finishes.
Status: Issued
| Sc Builders, Inc |
| $470K |
| applied Jul 17 | #202607175230 otc alterations permit 1st floor- interior non-structural demo only permit per ab-017 Status: Issued | B N Builders Inc | $300K |
| applied Dec 30 | #202512302985 otc alterations permit 3/f, 4/f, 5/f - partial demo of non structural walls, ceilings and light fixtures. new construction of non structural walls, finishes and power. mech and electr included. Status: Issued | B N Builders Inc | $1.9M |
| applied Dec 30 | #202512302974 otc alterations permit 2nd fl: tenan improvement for existing 2nd fl. partial demo and construction of interior partitions, ceilings, light fixtures. mep included.micro kitchen deferred for sfdph. Status: Issued | B N Builders Inc | $500K |
| applied Dec 18 | #202512182168 otc alterations permit ref 202506108301- documentation only for path of travel compliance of (e) high rise office buidling from street access and basement parking to first floor. scope does not inlcude levels above 1st floor. no work to be done and drawings record as built conditions complaint with cbc accessiblity Status: Complete | Not published | — |
| applied Jun 10 | #202506108301 otc alterations permit barrier removal improvements in high rise office bldg. bring basement floor parking accessibility up to current code. bring publicly accessible restrooms on 1st fl of 2 harrison & 345 spear up to current code Status: Complete | Skyline Construction | $150K |
In San Francisco, biggest first.