Commercial General Building work permitted December 10, 2024, with 23 permits through September 15, 2026, declaring $2,674,979 of work. Contractor on record: Skyline Construction.
7/f: architectural only office ti. new partitions, offices, and conference rooms. mep deferred.
San Francisco permit records name Skyline Construction, Bilcor Inc and Field Construction Inc. as the contractors on this project, among 5 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
23 permits issued Dec 10 – Sep 15, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Sep 15 | #202609158153 otc alterations permit |
Commercial and multifamily, biggest first.
to obtain final inspection under pa#: 202405142070. all work is complete.
Status: Issued
| Field Construction Inc. |
| — |
| applied Aug 26 | #202608267245 otc alterations permit to obtain final inspection for work approved under pa# 202503031385. all work is complete. Status: Issued | Field Construction Inc. | — |
| applied Mar 12 | #202603127431 otc alterations permit 7/f: two way ecs installation per fire comment on fire-26-119. install (1) cornell call station with signage. arch ref 202511200104. Status: Complete | Bilcor Inc | $3K |
| applied Feb 12 | #202602125820 otc alterations permit 7th floor: revision to pa#202511200104 to remove originally purposed drinking fountain, change layout of office 733, change copy room 729 to storage. Status: Complete | Skyline Construction | — |
| applied Feb 12 | #202602125818 otc alterations permit 7th floor: mechanical and electrical work for t.i. ref arch #202511200104 Status: Complete | Skyline Construction | $145K |
| applied Jan 30 | #202601304888 otc alterations permit 7th floor. relocate (24) pendants. add (14) pendents. ref pa# 202511200104 Status: Complete | Pioneer Fire Inc. | $23.6K |
| applied Nov 20 | #202511200104 otc alterations permit 7/f: architectural only office ti. new partitions, offices, and conference rooms. mep deferred. Status: Complete | Skyline Construction | $750K |
| applied Jul 17 | #202507170999 otc alterations permit 8th floor, suite 800. install 11 ceiing mount speaker - strobes and relocate 1 smoke detector. arch ref#: 202507019885. mech ref#: 202507019885. Status: Complete | Bilcor Inc | $11.3K |
| applied Jul 1 | #202507019885 otc alterations permit suite 800: mechanical, electrical, and plumbing for t.i. on the 8th floor. t.i. #202505156521. Status: Complete | Skyline Construction | $120K |
| applied Jun 23 | #202506239225 otc alterations permit suite 800: relocate (6) sprinkler heads. add (1) sprinkler head. referecne ti # 202505156521 Status: Complete | Pioneer Fire Inc. | $1.8K |
| applied Jun 18 | #202506188941 otc alterations permit install 16 control relays to shunt power to new electric controls for vav. ref mech pa 202405142070. Status: Issued | Bilcor Inc | $12.7K |
| applied May 29 | #202505297460 otc alterations permit install 8 ceiling mount speaker strobe. arch ref #202503263082 and mech ref #202505196786 Status: Complete | Bilcor Inc | $7.7K |
| applied May 19 | #202505196788 otc alterations permit 19/f suite 1950 - electrical work for t.i. ref permit 202503263082 Status: Complete | Skyline Construction | $45K |
| applied May 27 | #202505277251 otc alterations permit 19th fl- upgrades to 19th fl multi use restrooms. accessibility upgrades. new finishes, fixtures and lighting Status: Complete | Peacock Construction | $153K |
| applied May 19 | #202505196786 otc alterations permit 19/f suite 1950 - mechanical work for t.i. ref permit 202503263082 Status: Complete | Skyline Construction | $75K |
| applied May 15 | #202505156521 otc alterations permit 8th floor: t.i. : removal of non-structural partitions, new partitions and finishes. restroom accessibility upgrades. mep, life safety and sprinkler under seperate permit. Status: Complete | Skyline Construction | $350K |
| applied Apr 2 | #202504023578 otc alterations permit suite 1950; relocate (19) pendents gc ti#: 202503263082 Status: Complete | Pioneer Fire Inc. | $4.6K |
| applied Mar 26 | #202503263082 otc alterations permit suite #1950: t.i. on the 19th floor to include removal of non-structural partitions, new partitions, fixtures, finishes and restroom accessiblity upgrades. mechanical and electrical under seperate Status: Complete | Skyline Construction | $650K |
| applied May 29 | #202405142070 additions alterations or repairs changes made to the smoke control system by controls project.electronically controlled actuator added.a relay has been added which will drop power to these actuators.convert fan powered vav electronic control.relay to be added to each fl which will drop power to all the vav's. Status: Issued | Field Construction Inc. | $100K |
| applied Mar 7 | #202503071848 otc alterations permit 4th and 5th fl:relocate (2) plenum smoke detectors.install (2) plenum smoke detectors install (9) duct detectors install (2) control relay modules mech ref:2025-0303-1385 Status: Issued | Bilcor Inc | $30.7K |
| applied Mar 3 | #202503031385 otc alterations permit 4th & 5th fl - existing fire/smoke damper replacement are part of existing smoke controls upgrades. no changes made to existing smoke control system under proposed work scope. Status: Issued | Field Construction Inc. | $20K |
| applied Dec 19 | #202412197130 otc alterations permit 3/fl-ste. 300- ref 202407257231 and 202410223428- install (19) ceiling mount speaker strobe and (3) weatherproof ceiling mount speaker strobe, install (1) control relay Status: Complete | Bilcor Inc | $21.7K |
| applied Oct 22 | #202410223428 otc alterations permit 3/fl-ref 202407257231- electrical dn plumbing work for ti Status: Complete | Skyline Construction | $150K |
In San Francisco, biggest first.