Commercial General Building, Electrical, Fire Protection, Hvac/Mechanical, Plumbing work permitted October 29, 2024, with 95 permits through September 15, 2026, declaring $7,108,597 of work. Contractor on record: Rodgers Builders.
INTERIOR ALTERATIONS TO THE NOW VACATED SAME DAY SURGERY SPACE AND EXISTING ENDOSCOPY SUITE. PROJEC
Raleigh permit records name Rodgers Builders, C.T. Wilson Construction Compa and Newcomb & Company as the contractors on this project, among 19 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
95 permits issued Oct 29 – Sep 15, newest first.
| Issued |
|---|
Commercial and multifamily, biggest first.
| Permit |
|---|
| Contractor |
|---|
| Value |
|---|
#FIRE-038389-2026 FIRE - Fire Protection · Fire Alarm 480 sf Interior alterations to provide (2) new infusion bays and a new toilet room BUILDING IS 5 ST Status: Issued | Rodgers Builders | — | |
#FIRE-038392-2026 FIRE - Fire Protection · Fire Sprinklers 480 sf Interior alterations to provide (2) new infusion bays and a new toilet room BUILDING IS 5 ST Status: Issued | Rodgers Builders | — | |
| applied Jul 16 | #BLDNR-034474-2026 Building · Alteration/Repairs 480 sf Interior alterations to provide (2) new infusion bays and a new toilet room BUILDING IS 5 ST Status: Issued | Not published | $102K |
#PLMNR-038431-2026 DSINSP - Plumbing (Non-Residential) · Sub Permit 480 sf Interior alterations to provide (2) new infusion bays and a new toilet room BUILDING IS 5 ST Status: Issued | Hillsborough Plumbing Co., Inc | — | |
#MECHNR-038439-2026 DSINSP - Mechanical (Non-Residential) · Sub Permit 480 sf Interior alterations to provide (2) new infusion bays and a new toilet room BUILDING IS 5 ST Status: Issued | Newcomb & Company | — | |
#ELENR-038492-2026 DSINSP - Electrical (Non-Residential) · Sub Permit 480 sf Interior alterations to provide (2) new infusion bays and a new toilet room BUILDING IS 5 ST Status: Issued | System Electric Corporation | — | |
#FIRE-026013-2026 FIRE - Fire Protection · Fire Alarm We are modernizing the M1-M3 elevators at Duke Raleigh Hospital 2050 SF BUILDING IS 6 STORY W/BASE Status: Issued | Pavion Corp | — | |
| applied May 18 | #BLDNR-022796-2026 Building · Alteration/Repairs We are modernizing the M1-M3 elevators at Duke Raleigh Hospital 2050 SF BUILDING IS 6 STORY W/BASE Status: Issued | Not published | $252K |
#ELENR-025789-2026 DSINSP - Electrical (Non-Residential) · Sub Permit We are modernizing the M1-M3 elevators at Duke Raleigh Hospital 2050 SF BUILDING IS 6 STORY W/BASE Status: Issued | Starr Electric Company Inc. | — | |
#ELENR-056899-2025 DSINSP - Electrical (Non-Residential) · Sub Permit Existing vacant space on the ground floor of the hospital to become the plaza pharmacy to dispense m Status: Issued | Starr Electric Company Inc. | — | |
#FIRE-056892-2025 FIRE - Fire Protection · Fire Sprinklers Existing vacant space on the ground floor of the hospital to become the plaza pharmacy to dispense m Status: Issued | Rodgers Builders | — | |
| applied Oct 17 | #BLDNR-047812-2025 Building · Alteration/Repairs Existing vacant space on the ground floor of the hospital to become the plaza pharmacy to dispense m Status: Issued | Rodgers Builders | $174K |
#PLMNR-050535-2025 DSINSP - Plumbing (Non-Residential) · Sub Permit Existing vacant space on the ground floor of the hospital to become the plaza pharmacy to dispense m Status: Issued | Acme Plumbing & Heating Co. of Durham, Inc. | — | |
#MECHNR-050530-2025 DSINSP - Mechanical (Non-Residential) · Sub Permit Existing vacant space on the ground floor of the hospital to become the plaza pharmacy to dispense m Status: Issued | Newcomb & Company | — | |
#FIRE-056893-2025 FIRE - Fire Protection · Fire Alarm Existing vacant space on the ground floor of the hospital to become the plaza pharmacy to dispense m Status: Issued | Rodgers Builders | — | |
#ELENR-030055-2026 DSINSP - Electrical (Non-Residential) · Low Voltage Interior fit-up for a new Hybrid Operating Room in the existing Operating Room platform located on t Status: Issued | D. W. Evans Electric Inc. | — | |
#MENR-026611-2026 DSINSP - Online Only Mechanical (Non-Residential) · Ductwork (Repair/Replace Only) Adding 1 exhaust fan Status: Complete | Newcomb & Company | — | |
#FIRE-021930-2026 FIRE - Fire Protection · Compressed Gases Interior fit-up a new hybrid operating room in existing operating room platform located on the first Status: Issued | JE Dunn Construction | — | |
#FIRE-011973-2026 FIRE - Fire Protection · Fire Alarm Pavion to provide fire alarm system additions for the Duke DUKE RALEIGH HOSPITAL NEW SECURITY DOOR F Status: Complete | Pavion Corp | — | |
#ELENR-015481-2026 DSINSP - Electrical (Non-Residential) · Low Voltage Pavion to provide fire alarm system additions for the Duke DUKE RALEIGH HOSPITAL NEW SECURITY DOOR F Status: Issued | Pavion Corp | — | |
#ELENR-009508-2026 DSINSP - Electrical (Non-Residential) · Sub Permit Interior fit-up for a new Hybrid Operating Room in the existing Operating Room platform located on t Status: Issued | D. W. Evans Electric Inc. | — | |
#FIRE-009341-2026 FIRE - Fire Protection · Fire Sprinklers Interior fit-up for a new Hybrid Operating Room in the existing Operating Room platform located on t Status: Issued | Je Dunn Construction | — | |
#FIRE-009342-2026 FIRE - Fire Protection · Fire Alarm Interior fit-up for a new Hybrid Operating Room in the existing Operating Room platform located on t Status: Issued | Je Dunn Construction | — | |
#MECHNR-002283-2026 DSINSP - Mechanical (Non-Residential) · Sub Permit Interior fit-up for a new Hybrid Operating Room in the existing Operating Room platform located on t Status: Complete | MSS Solutions, LLC | — | |
#PLMNR-002284-2026 DSINSP - Plumbing (Non-Residential) · Sub Permit Interior fit-up for a new Hybrid Operating Room in the existing Operating Room platform located on t Status: Complete | Acme Plumbing & Heating Co. of Durham, Inc. | — | |
| applied Dec 20 | #BLDNR-057043-2025 Building · Alteration/Repairs Interior fit-up for a new Hybrid Operating Room in the existing Operating Room platform located on t Status: Issued | Je Dunn Construction | $281K |
| applied Oct 2 | #BLDNR-045585-2025 Building · Alteration/Repairs INTERIOR ALTERATIONS TO THE NOW VACATED SAME DAY SURGERY SPACE AND EXISTING ENDOSCOPY SUITE. PROJEC Status: Issued | Rodgers Builders | $2.3M |
| applied Nov 4 | #BLDNR-050521-2025 Building · Alteration/Repairs Existing vacant space that will be converted to a new chemistry lab with ancillary office and storag Status: Issued | Not published | $705K |
#PLMNR-053082-2025 DSINSP - Plumbing (Non-Residential) · Sub Permit Existing vacant space that will be converted to a new chemistry lab with ancillary office and storag Status: Complete | Brown Brother's Plumbing Heating and Air Condition | — | |
#MECHNR-053079-2025 DSINSP - Mechanical (Non-Residential) · Sub Permit Existing vacant space that will be converted to a new chemistry lab with ancillary office and storag Status: Complete | Newcomb & Company | — | |
#ELENR-057021-2025 DSINSP - Electrical (Non-Residential) · Sub Permit Existing vacant space that will be converted to a new chemistry lab with ancillary office and storag Status: Complete | D. W. Evans Electric Inc. | — | |
#FIRE-056944-2025 FIRE - Fire Protection · Fire Sprinklers Existing vacant space that will be converted to a new chemistry lab with ancillary office and storag Status: Complete | Rodgers Builders | — | |
#MECHNR-049993-2025 DSINSP - Mechanical (Non-Residential) · Sub Permit INTERIOR ALTERATIONS TO THE NOW VACATED SAME DAY SURGERY SPACE AND EXISTING ENDOSCOPY SUITE. PROJEC Status: Issued | Newcomb & Company | — | |
#FIRE-050025-2025 FIRE - Fire Protection · Fire Sprinklers INTERIOR ALTERATIONS TO THE NOW VACATED SAME DAY SURGERY SPACE AND EXISTING ENDOSCOPY SUITE. PROJEC Status: Issued | Rodgers Builders | — | |
#FIRE-056946-2025 FIRE - Fire Protection · Fire Alarm Existing vacant space that will be converted to a new chemistry lab with ancillary office and storag Status: Complete | Rodgers Builders | — | |
#PLMNR-049977-2025 DSINSP - Plumbing (Non-Residential) · Sub Permit INTERIOR ALTERATIONS TO THE NOW VACATED SAME DAY SURGERY SPACE AND EXISTING ENDOSCOPY SUITE. PROJEC Status: Issued | Acme Plumbing & Heating Co. of Durham, Inc. | — | |
#FIRE-050026-2025 FIRE - Fire Protection · Fire Alarm INTERIOR ALTERATIONS TO THE NOW VACATED SAME DAY SURGERY SPACE AND EXISTING ENDOSCOPY SUITE. PROJEC Status: Issued | Rodgers Builders | — | |
#ELENR-050124-2025 DSINSP - Electrical (Non-Residential) · Sub Permit INTERIOR ALTERATIONS TO THE NOW VACATED SAME DAY SURGERY SPACE AND EXISTING ENDOSCOPY SUITE. PROJEC Status: Issued | D. W. Evans Electric Inc. | — | |
#FIRE-047078-2025 FIRE - Fire Protection · Fire Sprinklers new security door within the existing PET/CT suite. Status: Complete | C.T. Wilson Construction Compa | — | |
| applied Sep 24 | #BLDNR-044109-2025 Building · Alteration/Repairs New security door within the existing PET/CT suite. Status: Complete | C.T. Wilson Construction Compa | $22K |
#ELENR-047089-2025 DSINSP - Electrical (Non-Residential) · Sub Permit new security door within the existing PET/CT suite. Status: Complete | Starr Electric Company Inc. | — | |
#ELENR-045577-2025 DSINSP - Electrical (Non-Residential) · Sub Permit Existing vacant area in the basement of the hospital where they would like to relocate their pharmac Status: Complete | D. W. Evans Electric Inc. | — | |
#FIRE-045488-2025 FIRE - Fire Protection · Fire Alarm Existing vacant area in the basement of the hospital where they would like to relocate their pharmac Status: Complete | C.T. Wilson Construction Compa | — | |
#PLMNR-041757-2025 DSINSP - Plumbing (Non-Residential) · Sub Permit Existing vacant area in the basement of the hospital where they would like to relocate their pharmac Status: Complete | Acme Plumbing Co., LLC | — | |
#MECHNR-041756-2025 DSINSP - Mechanical (Non-Residential) · Sub Permit Existing vacant area in the basement of the hospital where they would like to relocate their pharmac Status: Complete | Gallo Mechanical, LLC | — | |
| applied Aug 21 | #BLDNR-039013-2025 Building · Alteration/Repairs Existing vacant area in the basement of the hospital where they would like to relocate their pharmac Status: Issued | C.T. Wilson Construction Compa | $517K |
#FIRE-045487-2025 FIRE - Fire Protection · Fire Sprinklers Existing vacant area in the basement of the hospital where they would like to relocate their pharmac Status: Complete | C.T. Wilson Construction Compa | — | |
#PLMNR-047192-2025 DSINSP - Plumbing (Non-Residential) · Sub Permit Existing vacant ICU space on the 2nd floor of the hospital -6400SF they wish to convert this area to Status: Complete | Acme Plumbing & Heating Co. of Durham, Inc. | — | |
#MECHNR-044571-2025 DSINSP - Mechanical (Non-Residential) · Sub Permit Existing vacant ICU space on the 2nd floor of the hospital -6400SF they wish to convert this area to Status: Complete | Newcomb & Company | — | |
| applied Sep 16 | #BLDNR-042619-2025 Building · Alteration/Repairs Existing vacant ICU space on the 2nd floor of the hospital -6400SF they wish to convert this area to Status: Complete | C.T. Wilson Construction Compa | $1.3M |
#FIRE-045045-2025 FIRE - Fire Protection · Fire Sprinklers Existing vacant ICU space on the 2nd floor of the hospital -6400SF they wish to convert this area to Status: Complete | C.T. Wilson Construction Compa | — | |
#FIRE-045048-2025 FIRE - Fire Protection · Fire Alarm Existing vacant ICU space on the 2nd floor of the hospital -6400SF they wish to convert this area to Status: Complete | C.T. Wilson Construction Compa | — | |
#ELENR-047303-2025 DSINSP - Electrical (Non-Residential) · Sub Permit Existing vacant ICU space on the 2nd floor of the hospital -6400SF they wish to convert this area to Status: Complete | D. W. Evans Electric Inc. | — | |
#MECHNR-043462-2025 DSINSP - Mechanical (Non-Residential) · Sub Permit new rated walls around existing storage room I-2 OCC 1-A CONST 220 SF BUILDING IS 5 STORY WITH BASEM Status: Complete | Mechanical Contractors LLC | — | |
#FIRE-043818-2025 FIRE - Fire Protection · Fire Alarm new rated walls around existing storage room I-2 OCC 1-A CONST 220 SF BUILDING IS 5 STORY WITH BASEM Status: Complete | Rodgers Builders | — | |
#ELENR-043847-2025 DSINSP - Electrical (Non-Residential) · Sub Permit new rated walls around existing storage room I-2 OCC 1-A CONST 220 SF BUILDING IS 5 STORY WITH BASEM Status: Complete | South-Fair Electric Contractors, Inc | — | |
| applied Sep 8 | #BLDNR-041305-2025 Building · Alteration/Repairs New rated walls around existing storage room I-2 OCC 1-A CONST 220 SF BUILDING IS 5 STORY WITH BASEM Status: Complete | Rodgers Builders | $44.1K |
#FIRE-043821-2025 FIRE - Fire Protection · Fire Sprinklers new rated walls around existing storage room I-2 OCC 1-A CONST 220 SF BUILDING IS 5 STORY WITH BASEM Status: Complete | Rodgers Builders | — | |
#FIRE-026402-2025 FIRE - Fire Protection · Fire Alarm 500O SF I-2 OCC 1-A CONST 3 PHASES Interior alterations to the existing basement (north pavilion) o Status: Complete | C.T. Wilson Construction Compa | — | |
#ELENR-026947-2025 DSINSP - Electrical (Non-Residential) · Sub Permit 500O SF I-2 OCC 1-A CONST 3 PHASES Interior alterations to the existing basement (north pavilion) o Status: Complete | D. W. Evans Electric Inc. | — | |
| applied Feb 13 | #BLDNR-006693-2025 Building · Alteration/Repairs 500O SF I-2 OCC 1-A CONST 3 PHASES Interior alterations to the existing basement (north pavilion) o Status: Complete | C.T. Wilson Construction Compa | $967K |
#PLMNR-026986-2025 DSINSP - Plumbing (Non-Residential) · Sub Permit 500O SF I-2 OCC 1-A CONST 3 PHASES Interior alterations to the existing basement (north pavilion) o Status: Complete | Hillsborough Plumbing Co., Inc | — | |
#MECHNR-026985-2025 DSINSP - Mechanical (Non-Residential) · Sub Permit 500O SF I-2 OCC 1-A CONST 3 PHASES Interior alterations to the existing basement (north pavilion) o Status: Complete | Newcomb & Company | — | |
#FIRE-026400-2025 FIRE - Fire Protection · Fire Sprinklers 500O SF I-2 OCC 1-A CONST 3 PHASES Interior alterations to the existing basement (north pavilion) o Status: Complete | C.T. Wilson Construction Compa | — | |
#ELENR-015942-2025 DSINSP - Electrical (Non-Residential) · Sub Permit New discharge lounge in an existing vacant space on the ground floor of the hospital. Scope involve Status: Complete | D. W. Evans Electric Inc. | — | |
| applied Mar 12 | #BLDNR-010624-2025 Building · Alteration/Repairs New discharge lounge in an existing vacant space on the ground floor of the hospital. Scope involve Status: Complete | C.T. Wilson Construction Compa | $73.5K |
#MECHNR-012695-2025 DSINSP - Mechanical (Non-Residential) · Sub Permit New discharge lounge in an existing vacant space on the ground floor of the hospital. Scope involve Status: Complete | Newcomb & Company | — | |
#FIRE-015727-2025 FIRE - Fire Protection · Fire Alarm New discharge lounge in an existing vacant space on the ground floor of the hospital. Scope involve Status: Complete | C.T. Wilson Construction Compa | — | |
#FIRE-015726-2025 FIRE - Fire Protection · Fire Sprinklers New discharge lounge in an existing vacant space on the ground floor of the hospital. Scope involve Status: Complete | C.T. Wilson Construction Compa | — | |
#FIRE-010594-2025 FIRE - Fire Protection · Auto Fire Extinguishing System (Inert Gas) Interior alterations to upgrade existing cath lab with new equip and finishes. New hvac unit 1-A CON Status: Complete | C.T. Wilson Construction Compa | — | |
#FIRE-012046-2025 FIRE - Fire Protection · Compressed Gases 580 SF Equipment replacement for CT scanner. Includes new machine, new ACT ceiling, new patient lift Status: Complete | Rodgers Builders Inc. | — | |
#FIRE-012041-2025 FIRE - Fire Protection · Fire Alarm 580 SF Equipment replacement for CT scanner. Includes new machine, new ACT ceiling, new patient lift Status: Complete | Rodgers Builders Inc. | — | |
#PLMNR-010293-2025 DSINSP - Plumbing (Non-Residential) · Sub Permit 580 SF Equipment replacement for CT scanner. Includes new machine, new ACT ceiling, new patient lift Status: Complete | Purepipe Systems, LLC | — | |
#MECHNR-010291-2025 DSINSP - Mechanical (Non-Residential) · Sub Permit 580 SF Equipment replacement for CT scanner. Includes new machine, new ACT ceiling, new patient lift Status: Complete | Mechanical Contractors, LLC | — | |
#ELENR-010432-2025 DSINSP - Electrical (Non-Residential) · Low Voltage 580 SF Equipment replacement for CT scanner. Includes new machine, new ACT ceiling, new patient lift Status: Complete | Pathway Technologies, Inc. | — | |
#ELENR-010430-2025 DSINSP - Electrical (Non-Residential) · Sub Permit 580 SF Equipment replacement for CT scanner. Includes new machine, new ACT ceiling, new patient lift Status: Complete | South-Fair Electric Contractors, Inc | — | |
#FIRE-012044-2025 FIRE - Fire Protection · Fire Sprinklers 580 SF Equipment replacement for CT scanner. Includes new machine, new ACT ceiling, new patient lift Status: Complete | Rodgers Builders Inc. | — | |
| applied Feb 10 | #BLDNR-005854-2025 Building · Alteration/Repairs 580 SF Equipment replacement for CT scanner. Includes new machine, new ACT ceiling, new patient lift Status: Complete | Rodgers Builders | $112K |
#FIRE-011470-2025 FIRE - Fire Protection · Fire Sprinklers DUKE RALEIGH HOSPITAL CT scanner equipment replacement 610 SF BUILDNG IS TYPE 1-A CONST 5 STORY W/PE Status: Complete | Rodgers Builders | — | |
#FIRE-011417-2025 FIRE - Fire Protection · Compressed Gases DUKE RALEIGH HOSPITAL CT scanner equipment replacement 610 SF BUILDNG IS TYPE 1-A CONST 5 STORY W/PE Status: Complete | Rodgers Builders | — | |
| applied Dec 20 | #BLDNR-061767-2024 Building · Alteration/Repairs Addition of thicker lead shielding on existing walls in the PET/CT suite Status: Complete | C.T. Wilson Construction Compa | $19.3K |
#ELENR-001706-2025 DSINSP - Electrical (Non-Residential) · Sub Permit Addition of thicker lead shielding on existing walls in the PET/CT suite Status: Complete | Starr Electric Company Inc. | — | |
#PLMNR-000173-2025 DSINSP - Plumbing (Non-Residential) · Sub Permit Addition of thicker lead shielding on existing walls in the PET/CT suite Status: Complete | Acme Plumbing & Heating Co. of Durham, Inc. | — | |
#PLMNR-035594-2024 DSINSP - Plumbing (Non-Residential) · Sub Permit Interior alterations to upgrade existing cath lab with new equip and finishes. New hvac unit 1-A CON Status: Complete | Acme Plumbing & Heating Co. of Durham, Inc. | — | |
#MECHNR-035591-2024 DSINSP - Mechanical (Non-Residential) · Sub Permit Interior alterations to upgrade existing cath lab with new equip and finishes. New hvac unit 1-A CON Status: Complete | Newcomb & Company | — | |
#FIRE-035680-2024 FIRE - Fire Protection · Compressed Gases Interior alterations to upgrade existing cath lab with new equip and finishes. New hvac unit 1-A CON Status: Complete | Associated Fire Protection | — | |
#FIRE-035652-2024 FIRE - Fire Protection · Fire Alarm Interior alterations to upgrade existing cath lab with new equip and finishes. New hvac unit 1-A CON Status: Complete | Pavion Corp | — | |
#FIRE-035675-2024 FIRE - Fire Protection · Fire Sprinklers Interior alterations to upgrade existing cath lab with new equip and finishes. New hvac unit 1-A CON Status: Complete | Associated Fire Protection | — | |
| applied Jul 2 | #BLDNR-032822-2024 Building · Alteration/Repairs Interior alterations to upgrade existing cath lab with new equip and finishes. New hvac unit 1-A CON Status: Complete | C.T. Wilson Construction Compa | $135K |
#ELENR-037362-2024 DSINSP - Electrical (Non-Residential) · Sub Permit Interior alterations to upgrade existing cath lab with new equip and finishes. New hvac unit 1-A CON Status: Complete | Starr Electric Company Inc. | — | |
#PLMNR-051567-2024 DSINSP - Plumbing (Non-Residential) · Sub Permit DUKE RALEIGH HOSPITAL CT scanner equipment replacement 610 SF BUILDNG IS TYPE 1-A CONST 5 STORY W/PE Status: Complete | Purepipe Systems, LLC | — | |
#FIRE-050622-2024 FIRE - Fire Protection · Fire Alarm DUKE RALEIGH HOSPITAL CT scanner equipment replacement 610 SF BUILDNG IS TYPE 1-A CONST 5 STORY W/PE Status: Complete | Rodgers Builders | — | |
#MECHNR-048183-2024 DSINSP - Mechanical (Non-Residential) · Sub Permit DUKE RALEIGH HOSPITAL CT scanner equipment replacement 610 SF BUILDNG IS TYPE 1-A CONST 5 STORY W/PE Status: Complete | Mechanical Contractors, LLC | — | |
#ELENR-048035-2024 DSINSP - Electrical (Non-Residential) · Sub Permit DUKER RALEIGH HOSPITAL CT scanner equipment replacement 610 SF BUILDNG IS TYPE 1-A CONST 5 STORY W/P Status: Complete | South-Fair Electric Contractors, Inc | — | |
| applied Sep 3 | #BLDNR-044121-2024 Building · Alteration/Repairs DUKE RALEIGH HOSPITAL CT scanner equipment replacement 610 SF BUILDNG IS TYPE 1-A CONST 5 STORY W/PE Status: Complete | Rodgers Builders | $118K |