How long commercial permits take in Raleigh, by trade
Median days from application to issue and median declared value, commercial and multifamily permits issued July 31, 2026 – October 29, 2026.
| Trade | Permits | Median days to issue | Median declared value |
|---|---|---|---|
| Building | 370 | 56 | $112K |
Counts only permits whose record includes an application date (353 of 2,147). Times depend on the city’s review track: express and over-the-counter trade permits often issue within days, new construction takes longer.
Most common commercial permit types
- DSINSP - Electrical (Non-Residential)489
- FIRE - Fire Protection370
- Building353
- DSINSP - Mechanical (Non-Residential)306
- DSINSP - Plumbing (Non-Residential)258
- DSINSP - Online Only Electrical (Non-Residential)245