Get ProEvery project in every city · from $79/mo
Get Procommercial project · Pittsburgh, PA
Commercial General Building, Demolition, Electrical, Fire Protection, Hvac/Mechanical work permitted February 9, 2026, with 9 permits through August 19, 2026, declaring $8,872,291 of work. Contractor on record: Interstate Fire Protection Co Inc.
PHASED CONSTRUCTION ABOVE-GROUND CONSTRUCTION OF A NEW SALT STORAGE FACILITY WITH AN EMPLOYEE BREAK ROOM AND (2) SINGLE-USE BATHROOMS. THE FACILITY IS CONSTRUCTED OF CAST-IN-PLACE CONCRETE WALLS / FOUNDATIONS WITH A WOOD-FRAMED UPPER WALL & PRE-ENGINEERED WOOD ROOF TRUSSES.
Pittsburgh permit records name Interstate Fire Protection Co Inc, Sargent Electric Co and Minniefield Demolition Services, LLC as the contractors on this project, among 4 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
9 permits issued Feb 9 – Aug 19, newest first.
Commercial and multifamily, biggest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
#SSP-2026-04193 Suppression System Permit · NEW SYSTEM ABOVE-GROUND SUPPRESSION WORK FOR A NEW SALT STORAGE FACILITY WITH AN EMPLOYEE BREAK ROOM AND (2) SINGLE-USE BATHROOMS. RELATED TO BDA-2025-04100. UNDERGROUND SUPPRESSION PERMIT: SSP-2026-05331. Status: Issued | Interstate Fire Protection Co Inc | $137K | |
#SSP-2026-05331 Suppression System Permit · NEW SYSTEM UNDERGROUND SUPPRESSION WORK FOR A NEW SALT STORAGE FACILITY WITH AN EMPLOYEE BREAK ROOM AND (2) SINGLE-USE BATHROOMS. RELATED TO BDA-2025-04100. ABOVE-GROUND SUPPRESSION PERMIT SSP-2026-04193. Status: Issued | Interstate Fire Protection Co Inc | $30K | |
#FAS-2026-02038 Fire Alarm Permit · NEW SYSTEM UNSEPARATED BUSINESS & S-2 STORAGE AREA REQUIREMENTS IN TYPE VB CONSTRUCTION & EXISTING HYDRANT FLOWS REQUIRE BUILDING SUPPRESSION THROUGHOUT WITH FIRE ALARM FOR SUPPRESSON SYSTEN MONITORING. THIS IS A PHASED CONSTRUCTION PERMIT. ABOVE-GROUND CONSTRUCTION OF A NEW SALT STORAGE FACILITY WITH AN… Status: Issued | Sargent Electric Co | $30K | |
#EP-2025-02995 ELECTRICAL · NEW CONSTRUCTION ELECTRICAL WORK FOR ABOVE-GROUND CONSTRUCTION OF A NEW SALT STORAGE FACILITY WITH EMPLOYEE BREAK ROOM AND (2) SINGLE-USE BATHROOMS. ELECTRICAL WORK INCLUDES NEW SERVICE, METER, PANELBOARD, WIRING, LIGHTING, & POWER FOR THE NEW SALT STORAGE FACILITY. Status: Issued | Sargent Electric Co | $300K | |
#BDA-2025-04100 Building & Development Application · New Construction PHASED CONSTRUCTION ABOVE-GROUND CONSTRUCTION OF A NEW SALT STORAGE FACILITY WITH AN EMPLOYEE BREAK ROOM AND (2) SINGLE-USE BATHROOMS. THE FACILITY IS CONSTRUCTED OF CAST-IN-PLACE CONCRETE WALLS / FOUNDATIONS WITH A WOOD-FRAMED UPPER WALL & PRE-ENGINEERED WOOD ROOF TRUSSES. Status: Issued | Not published | $8M | |
#BDA-2026-02218 Building & Development Application · New Construction PHASED CONSTRUCTION FOR THE FOUNDATION AND FIRST-FLOOR PERIMETER CONCRETE WALLS OF A NEW SALT STORAGE FACILITY Status: Issued | Not published | — | |
#DP-2025-02985 Demolition Permit · COMPLETE DEMOLITION COMPLETE DEMOLITION OF EXISTING CONCRETE SALT STORAGE DOME BUILDING. Status: Completed | Minniefield Demolition Services, LLC | $97.1K | |
#DP-2026-00725 Demolition Permit · COMPLETE DEMOLITION DEMO 2 STORY STRUCTURE (CAFE) SITE SHEDS AND ASPHALT PAVING; SALT DOME IS DEMOLISHED UNDER DP-2025-02985 Status: Completed | Minniefield Demolition Services, LLC | $263K | |
#MP-2026-00796 MECHANICAL · MINOR ALTERATION Status: Issued | Air Systems Mechanical Contracting Inc | $45K |
In Pittsburgh, biggest first.