Commercial General Building, Hvac/Mechanical, Plumbing work permitted May 20, 2026, with 5 permits through July 2, 2026, declaring $133,350,054 of work. Contractor on record: Turner Ee Cruz A Joint.
Get new commercial permits near 10280 or New York City, free weekly email
Reach 6-New flood wall constr. for NWBPCR project. Scope includes excavation, grading, landscaping, soil improvement. Add & compact fill to stabilize site with erosion cont. Stabilize foundations of adj. structures. No change to use, egress or occupancy.
New York City permit records name Turner Ee Cruz A Joint and Madison Pipe Consult Inc as the contractors on this project.
The property owner is included with Pro.
5 permits issued May 20 – Jul 2, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Dec 21 |
Commercial and multifamily, biggest first.
#M01238963-I1-GC-CX General Construction · Initial Permit Reach 6-New flood wall constr. for NWBPCR project. Scope includes excavation, grading, landscaping, soil improvement. Add & compact fill to stabilize site with erosion cont. Stabilize foundations of adj. structures. No change to use, egress or occupancy. Status: Permit Issued |
| Turner Ee Cruz A Joint |
| $82.5M |
| applied Dec 21 | #M01238963-S1-GC-CX General Construction · Initial Permit Reach 6 - The FBS includes micropile-founded T-walls, L-walls, founded closure gates at street crossings (roller gates at Thames, Rector, Albany), stoplogs for Gateway Plaza pool access, & an integral tide gatewell. No change to use, egress or occupancy. Status: Permit Issued | Turner Ee Cruz A Joint | $47.4M |
| applied Dec 23 | #M01238963-S4-MS Mechanical Systems · Initial Permit REACH 6 - TEMPORARY RELOCATION OF HVAC UNIT TO COMPLETE CONSTRUCTION OF FLOOD BARRIER SYSTEM FOR THE BPCA NORTH/WEST BATTERY PARK CITY RESILIENCY PROJECT. NO CHANGE TO USE, EGRESS OR OCCUPANCY. Status: Permit Issued | Turner Ee Cruz A Joint | $562K |
| applied Mar 3 | #M01238963-S2-SE Support of Excavation · Initial Permit Scope of Work: Reach 6 - Construction of flood barrier system for the BPCA north/west battery park city resiliency project includes Support of excavation work. No change to use, egress or occupancy. Status: Permit Issued | Turner Ee Cruz A Joint | $2.5M |
| applied Dec 23 | #M01238963-S3-PL Plumbing · Initial Permit Reach 6 - Relocate 12 watermains; install valves/boxes at West Thames, Rector, Albany, Gateway. Move hydrant; replace temp waterlines. Install tide gates, manholes, drains, sump pump. Replace storm outfalls, sewers. No change to use, egress or occupancy. Status: Permit Issued | Madison Pipe Consult Inc | $425K |