Commercial General Building, Hvac/Mechanical, Plumbing work permitted March 4, 2025, with 4 permits through June 18, 2025, declaring $27,637,265 of work. Contractor on record: Schadegg Mechanical.
Get new commercial permits in Minneapolis, free weekly email
construct new 4 story office and enclosed parking garage. garage consists of 2 levels, one structurally supported. CERTIFICATE OF OCCUPANCY REQUIRED CONST TYPE: 2b NUMBER OF STORIES: 4 OCCUPANCY: B, S1, S2, A3 2020 MSBC SPRINKLERED:
Minneapolis permit records name Schadegg Mechanical, Klamm Mechanical Contractors Inc and Knutson Construction as the contractors on this project.
4 permits issued Mar 4 – Jun 18, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
In Minneapolis, biggest first.
#BLDG1125514 Plumbing · ComMin Connect drainage to two new lift bays Status: Closed |
| Klamm Mechanical Contractors Inc |
| — |
#BLDG1115722 Plumbing · NewCom Xcel/Install plumbing systems in new building All plumbing shall be installed in accordance with the 2020 Minnesota State Plumbing Code (MSPC), Chapter 4714. All pipe, pipe fittings, traps, fixtures, material, and devices used in the plumbing syste Status: Closed | Schadegg Mechanical | — |
#BLDG1115712 Mechanical · ComMFDNR HVAC system for 4 stories office building plus a parking garage space. Installing of air handling units, energy recovery ventilators, exhaust fans, make-up air unit, split systems, and VAV boxes. Installation of chilled water, hot water, and boiler recirc Status: Closed | Schadegg Mechanical | $4.8M |
#BLDG1094667 Commercial · New construct new 4 story office and enclosed parking garage. garage consists of 2 levels, one structurally supported. CERTIFICATE OF OCCUPANCY REQUIRED CONST TYPE: 2b NUMBER OF STORIES: 4 OCCUPANCY: B, S1, S2, A3 2020 MSBC SPRINKLERED: Status: Closed | Knutson Construction | $22.8M |