Commercial General Building, Electrical, Elevator, Fire Protection work permitted January 23, 2025, with 9 permits through October 21, 2026, declaring $15,415,969 of work. Contractor on record: Affinity Service Electric LLC.
Replace existing site chilled-water supply and return piping serving Buildings 510, 520, 521, 530, 531, 533, 540, 543, 560, 580, 581 and 591, including new isolation valves, building connections, trenching, backfill and site restoration. Install two new 200-HP tertiary chilled-water pumps at Building 541, associated pump pedestal, structural pipe supports and foundations, and electrical modifications. No new water meters. Special inspections for post-installed anchors, structural steel, concrete and soils. Results in CofC.
Mesa permit records name Affinity Service Electric LLC, Caliente Construction, Inc and Pueblo Mechanical & Controls, LLC as the contractors on this project, among 6 contractors in all.
Phone numbers and the property owner are included with Pro, where the city publishes them.
In Mesa, biggest first.
9 permits issued Jan 23 – Oct 21, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Jul 13 | #PMT26-12849 Commercial Permit · Commercial/Industrial Projects Install canopy (427 SF) over existing electrical switchgear at Boeing substation. Special inspections required: steel construction, concrete construction, soils, high strength bolting, and post-installed anchors. Results in CofC. Status: Issued | Contractor with Pro | $15.3K |
| applied Sep 3 | #PMT26-16179 Commercial Permit · Commercial/Industrial Projects New 12 inch looped fire line extension to provide service connections to Building 570 and a potential expansion. Status: Issued | Contractor with Pro | $4.8M |
| applied Jul 13 | #PMT26-12883 Commercial Permit · Other Commercial Replace existing site chilled-water supply and return piping serving Buildings 510, 520, 521, 530, 531, 533, 540, 543, 560, 580, 581 and 591, including new isolation valves, building connections, trenching, backfill and site restoration. Install two new 200-HP tertiary chilled-water pumps at… Status: Issued | Caliente Construction, Inc | $5.9M |
| applied Jan 7 | #PMT26-00533 Commercial Permit · Commercial/Industrial Projects Grade and pave area with new asphalt. Renovate retention area. Results in CoC. Status: Issued | Affinity Service Electric LLC | — |
| applied Sep 16 | #PMT25-16500 Commercial Permit · Commercial/Industrial Projects Dewpoint control for building 570. Scope includes addition of a makeup air handler and low temperature chilled water system. Special inspections for steel, concrete, fabrication, and post-installed anchors. Deferred fire sprinklers and fire alarm. Results in CoC. Status: Issued | Pueblo Mechanical & Controls, LLC | $627K |
| applied Jan 20 | #AFP26-01140 Annual Facilities Permit Annual Facilities Permit for 2026 Status: Issued | The Boeing Company | — |
| applied Jun 17 | #PMT25-11133 Commercial Permit · Tenant Improvement (Interior Only) Tenant improvement in existing 158,529 SF, type II-B construction, F1, B and S1 occupancy warehouse to add 4,000 Sf, group B occupancy office mezzanine. Mezzanine to have Open office space, room for conferences and office, (2) stair access with (1) access to mezzanine hard lid that house new… Status: C Of O Issued | Affinity Service Electric LLC | $4.1M |
| applied Oct 13 | #PMT25-18575 Commercial Permit · Commercial/Industrial Projects DESIGN FOR A NEW FALCON2 MEDIUM VOLTAGE SWITCHGEAR FOR THE NEW SRP TRANSFORMER. THE NEW SWITCHGEAR WILL PROVIDE THE POWER FEED FOR THE NEW ACA PHASE 2 AND PHASE 3 ADDITION. Status: Issued | Pacific International Electric Company | — |
| applied Jan 17 | #PMT25-01104 Commercial Permit · Commercial/Industrial Projects Refer to AFP25-01081: Replace existing elevator equipment Status: Finaled - C Of C Required | Basalt Building Group LLC | — |