How long commercial permits take in Mesa, by trade
Median days from application to issue and median declared value, commercial and multifamily permits issued July 31, 2026 – October 29, 2026.
| Trade | Permits | Median days to issue | Median declared value |
|---|---|---|---|
| Building | 192 | 63 | $454K |
| Fire protection | 100 | 105 | $158K |
| Electrical | 61 | 41 | $20.5K |
| Signs | 22 | 32 | — |
| MEP | 9 | 138 | $640K |
| Plumbing | 9 | 8 | $2.6K |
| Demolition | 6 | 23 | — |
Counts only permits whose record includes an application date (424 of 424). Times depend on the city’s review track: express and over-the-counter trade permits often issue within days, new construction takes longer.