Commercial General Building work permitted November 26, 2025, with 3 permits through September 29, 2026, declaring $1,553,241 of work.
**ePlan**LAX**Structural and Architectural work related to replacing the virtual docking guidance systems (VDGS) for all united gates at LAX terminals 7 and 8. The scope is to remove the existing VDGS system at each gate. Alter and add new structural supports and repair any facade damage associated with the construction.
Los Angeles’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
3 permits issued Nov 26 – Sep 29, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Aug 11 | #26016-10000-21095 Bldg-Alter/Repair · Building **ePlan**LAX**Remove existing self serve kiosks. Status: Issued | Not published | $250K |
Commercial and multifamily, biggest first.
#25016-10000-33625 Bldg-Alter/Repair · Building **ePlan**LAX**Structural and Architectural work related to replacing the virtual docking guidance systems (VDGS) for all united gates at LAX terminals 7 and 8. The scope is to remove the existing VDGS system at each gate. Alter and add new structural supports and repair any facade damage… Status: Issued |
| Not published |
| $1.3M |
| applied Sep 26 | #25016-10000-28909 Bldg-Alter/Repair · Building **ePlan**LAX**T.I. for CLEAR at Terminal 7. Project includes removing (1) TSA document checker podium at the Security Checkpoint and installing (2) electronic gates. (No new floor area. No occupancy type or load changed) Status: Issued | Not published | $10K |