Commercial General Building, Demolition work permitted January 30, 2025, with 14 permits through October 23, 2026, declaring $2,301,638,497 of work.
**ePlan**LAX** Rebuild and addition for Terminal 05 at LAX Airport.
Los Angeles’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
14 permits issued Jan 30 – Oct 23, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
| applied Sep 22 | #25014-10011-03198 Bldg-Alter/Repair · Building EplanLAX PROJECT: TERMINAL 5 SUPPLEMENTAL TO PERMIT #25014-10000-03198 ; DEFERRED SUBMITTAL FOR SEISMIC BRACING FOR TELECOM CABLE TRAY SYSTEM. Status: Issued | Not published | $20K |
Commercial and multifamily, biggest first.
#25014-10010-03198 Bldg-Alter/Repair · Building **ePlan**LAX** Supplemental permit to 25014-10000-03198 : Deferred submittal ENGINEREED SEISMIC BRACING FOR ELECTRICAL, FIRE ALARM, AND TELECOM SYSTEMS. SEGMENT 1 AND 2, LEVELS 2-4. Status: Issued |
| Not published |
| $501 |
| applied Sep 8 | #25014-10007-03198 Bldg-Alter/Repair · Building Supplemental permit to 25014-10000-03198 Fireproofing detils to include the applicable UL assemblies details. Status: Issued | Not published | $501 |
| applied Jul 21 | #26030-10000-06046 Grading · Building LAX project:grading for temporary shoring for utility installation Status: Issued | Not published | $1.7K |
| applied Jul 21 | #26020-10000-01483 Nonbldg-New · Building LAX project:Temporary shoring for utility installation Status: Issued | Not published | $10K |
| applied Jul 30 | #25014-10000-03198 Bldg-Addition · Building **ePlan**LAX** Rebuild and addition for Terminal 05 at LAX Airport. Status: Issued | Not published | $2B |
| applied Jan 22 | #25014-10002-03198 Bldg-Alter/Repair · Building LAX Terminal 5 Early Start Foundations permit Status: Issued | Not published | $333M |
| applied Jan 22 | #26030-10000-00465 Grading · Building Site Grading for reconstruction of Terminal 05 at LAX Airport. Status: Issued | Not published | $51.3K |
| applied Feb 2 | #26020-10000-00176 Nonbldg-New · Building **ePlan**LAX**T5 Rebuild** Temporary earth retaining system containing soldier beams/ tiebacks and wood lagging. Status: Issued | Not published | $750K |
| applied Feb 2 | #26030-10000-01694 Grading · Building **ePlan**LAX** T5 rebuild**Grading work for Temporary earth retaining system containing soldier beams/ tiebacks and wood lagging. Status: Issued | Not published | $51 |
| applied Aug 25 | #25019-10000-02950 Bldg-Demolition · Building **ePlan**LAX**Demolition of Terminal 5 Headhouse and Concourse. Status: Issued | Not published | $800K |
| applied Feb 13 | #22014-10001-05919 Bldg-Alter/Repair · Building SUPPLEMENTAL PLAN CHECK TO #21014-10000-05919LAX TERMINAL 5 LEVEL 1 BAGAGGE STORAGE OFFICE UPDATES. REDUCED PERMITTED BAGGAGE STORAGE ROOM SIZE AND ADDED OFFICE. UPDATING RATED WALLS AND CEILING LAYOUTS ON ARCH. AND LS DRAWINGS. Status: Issued | Not published | $5K |
| applied Jul 9 | #22016-10004-28938 Bldg-Alter/Repair · Building LAX projectT5 CTX - Recapitalization Baggage Handling System(BHS) at CBIS. Scope includes improvements to the BHS and replacement of 4 EDS machines and installation of new BHS conveyors, controls and BHS devices. Status: Permit Finaled | Not published | $501 |
| applied Jul 30 | #22016-10005-28938 Bldg-Alter/Repair · Building **ePlan**LAX**Project Under Construction**Deferred submittal for permit number 22016-10000-28938 : seismic submittal for AHU Anchorage for Terminal 5 CTX Status: Permit Finaled | Not published | $501 |