Get ProEvery project in every city · from $79/mo
Get Procommercial project · Charlotte, NC
Commercial General Building, Electrical, Fire Protection, Hvac/Mechanical work permitted July 10, 2026, with 4 permits through July 10, 2026, declaring $645,000 of work.
PRESSURIZATION SYSTEM REPLACEMENT AS OUTLINED IN DEWBERRY SCHEMATIC DESIGN NARRATIVE DATED NOVEMBER 6, 2025. THE INTENT OF THIS DESIGN EFFORT IS TO REPLACE EXISTING SMOKE CONTROL SYSTEM WITH NEW COMPONENTS AND CONTROLS TO MEET CURRENT CODE AND FACILITATE CONNECTION OF NEW PATIENT BED TOWER INTO DIXON TOWER STAIR 19 ON 2ND AND 3RD FLOORS.
Charlotte’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
4 permits issued Jul 10 – Jul 10, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
#COM-ALT-26-001092 Alteration · Construction PRESSURIZATION SYSTEM REPLACEMENT AS OUTLINED IN DEWBERRY SCHEMATIC DESIGN NARRATIVE DATED NOVEMBER 6, 2025. THE INTENT OF THIS DESIGN EFFORT IS TO REPLACE EXISTING SMOKE CONTROL SYSTEM WITH NEW COMPONENTS AND CONTROLS TO MEET CURRENT CODE AND FACILITATE CONNECTION OF NEW PATIENT BED TOWER INTO… |
Commercial and multifamily, biggest first.
Status: Inspection Phase
| Not published |
| $645K |
#COM-ELC-26-006635 Electrical · Construction Provide electrical design to support stair pressurization fan power and supporting fire alarm system provisions. Status: Inspection Phase | Not published | — |
#COM-MEC-26-003234 Mechanical · Construction Provide mechanical design to support stair pressurization, system replacement including fan and associated dampers. Status: Inspection Phase | Not published | — |
#COM-FIRE-LIFE-26-000042 Fire · Construction (HR) Stair 19 Pressurization System Replacement DPR Construction, A General Partnership Status: Inspection Phase | Not published | — |