Get Promultifamily project · Charlotte, NC
Multifamily General Building, Electrical, Fire Protection, Hvac/Mechanical, Plumbing work permitted January 27, 2026, with 57 permits through October 28, 2026, declaring $10,300,038 of work.
Build out of the interior for the Level 10 amenity space
Charlotte’s permit records for this address don’t name a contractor; the permits list the scope, value and dates below.
57 permits issued Jan 27 – Oct 28, newest first.
| Issued | Permit | Contractor | Value |
|---|---|---|---|
#COM-ELC-26-010787 Electrical · Construction Pulled Fiber and cat6 from telco room to each unit. pulled cat6 from panel location in each unit to living room location. Status: Inspection Phase |
Commercial and multifamily, biggest first.
| Not published |
| — |
#COM-ELC-26-010592 Electrical · Construction Interior build out of residential units on Level 14. Unit numbers: 1401, 1402, 1403, 1404, 1405, 1406, 1407, 1408, 1409, 1410, 1411, 1412, 1413, 1414, 1415, 1416, 1417, 1418, 1419, 1420, 1421 Status: Inspection Phase | Not published | — |
#COM-FIRE-LIFE-26-000978 Fire · Construction Interior build out of residential units on Level 14. Unit numbers: 1401, 1402, 1403, 1404, 1405, 1406, 1407, 1408, 1409, 1410, 1411, 1412, 1413, 1414, 1415, 1416, 1417, 1418, 1419, 1420, 1421 Status: Inspection Phase | Not published | — |
#COM-PLM-26-002893 Plumbing · Construction Interior build out of residential units on Level 14. Unit numbers: 1401, 1402, 1403, 1404, 1405, 1406, 1407, 1408, 1409, 1410, 1411, 1412, 1413, 1414, 1415, 1416, 1417, 1418, 1419, 1420, 1421 Status: Inspection Phase | Not published | — |
#COM-MEC-26-005374 Mechanical · Construction Interior build out of residential units on Level 14. Unit numbers: 1401, 1402, 1403, 1404, 1405, 1406, 1407, 1408, 1409, 1410, 1411, 1412, 1413, 1414, 1415, 1416, 1417, 1418, 1419, 1420, 1421 Status: Inspection Phase | Not published | — |
#COM-NEW-26-000483 New · Construction Interior build out of residential units on Level 14. Unit numbers: 1401, 1402, 1403, 1404, 1405, 1406, 1407, 1408, 1409, 1410, 1411, 1412, 1413, 1414, 1415, 1416, 1417, 1418, 1419, 1420, 1421 Status: Inspection Phase | Not published | $2.2M |
#COM-FIRE-LIFE-26-000961 Fire · Construction Interior build out of residential units on Level 12. Unit numbers: 1201, 1202, 1203, 1204, 1205, 1206, 1207, 1208, 1209, 1210, 1211, 1212, 1213, 1214, 1215, 1216, 1217, 1218, 1219, 1220, 1221 Status: Inspection Phase | Not published | — |
#COM-PLM-26-002874 Plumbing · Construction Interior build out of residential units on Level 12. Unit numbers: 1201, 1202, 1203, 1204, 1205, 1206, 1207, 1208, 1209, 1210, 1211, 1212, 1213, 1214, 1215, 1216, 1217, 1218, 1219, 1220, 1221 Status: Inspection Phase | Not published | — |
#COM-MEC-26-005351 Mechanical · Construction Interior build out of residential units on Level 12. Unit numbers: 1201, 1202, 1203, 1204, 1205, 1206, 1207, 1208, 1209, 1210, 1211, 1212, 1213, 1214, 1215, 1216, 1217, 1218, 1219, 1220, 1221 Status: Inspection Phase | Not published | — |
#COM-ELC-26-010546 Electrical · Construction Interior build out of residential units on Level 12. Unit numbers: 1201, 1202, 1203, 1204, 1205, 1206, 1207, 1208, 1209, 1210, 1211, 1212, 1213, 1214, 1215, 1216, 1217, 1218, 1219, 1220, 1221 Status: Inspection Phase | Not published | — |
#COM-NEW-26-000481 New · Construction Interior build out of residential units on Level 12. Unit numbers: 1201, 1202, 1203, 1204, 1205, 1206, 1207, 1208, 1209, 1210, 1211, 1212, 1213, 1214, 1215, 1216, 1217, 1218, 1219, 1220, 1221 Status: Inspection Phase | Not published | $2.2M |
#COM-ELC-26-010186 Electrical · Construction LV -pulled fiber and cat6 from telco location to each unit. Pulled cat6 in each unit at living room loation. Status: Inspection Phase | Not published | — |
#COM-ELC-26-010189 Electrical · Construction LV - pulled fiber and cat6 from telco location to each unit. Pulled cat6 in each unit at living room loation. Status: Inspection Phase | Not published | — |
#COM-PLM-26-002811 Plumbing · Construction Plumbing build out of the interior for the level 10 amenity space Status: Inspection Phase | Not published | — |
#COM-MEC-26-005146 Mechanical · Construction Commercial New Construction Permit for COM-NEW-26-000471 Status: Inspection Phase | Not published | — |
#COM-NEW-26-000471 New · Construction Build out of the interior for the Level 10 amenity space Status: Inspection Phase | Not published | $4.2M |
#COM-FIRE-LIFE-26-000890 Fire · Construction Level 10 Amenity Space Status: Inspection Phase | Not published | — |
#COM-ELC-26-010165 Electrical · Construction Electrical build out of the interior for the level 10 amenity space Status: Inspection Phase | Not published | — |
#COM-ELC-26-010192 Electrical · Construction LV - pulled fiber and cat6 from telco location to each unit. Pulled cat6 in each unit at living room location. Status: Inspection Phase | Not published | — |
#COM-ELC-26-009238 Electrical · Construction Electrical build out of residential units on Level 10. Unit numbers: 1001, 1002, 1003, 1004, 1005, 1006, 1007, 1008, 1009, 1010, 1011, 1012. Status: Inspection Phase | Not published | — |
#COM-NEW-26-000402 New · Construction Interior build out of residential units on Level 11. Unit numbers: 1101, 1102, 1103, 1104, 1105, 1106, 1107, 1108, 1109, 1110, 1111, 1112, 1113, 1114, 1115, 1116, 1117, 1118, 1119, 1120, 1121 Status: Inspection Phase | Not published | $2.2M |
#COM-ELC-26-009322 Electrical · Construction Electrical build out of residential units on Level 11. Unit numbers: 1101, 1102, 1103, 1104, 1105, 1106, 1107, 1108, 1109, 1110, 1111, 1112, 1113, 1114, 1115, 1116, 1117, 1118, 1119, 1120, 1121. Status: Inspection Phase | Not published | — |
#COM-MEC-26-004736 Mechanical · Construction Mechanical build out of residential units on Level 11. Unit numbers: 1101, 1102, 1103, 1104, 1105, 1106, 1107, 1108, 1109, 1110, 1111, 1112, 1113, 1114, 1115, 1116, 1117, 1118, 1119, 1120, 1121. Status: Inspection Phase | Not published | — |
#COM-PLM-26-002572 Plumbing · Construction Plumbing build out of residential units on Level 11. Unit numbers: 1101, 1102, 1103, 1104, 1105, 1106, 1107, 1108, 1109, 1110, 1111, 1112, 1113, 1114, 1115, 1116, 1117, 1118, 1119, 1120, 1121. Status: Inspection Phase | Not published | — |
#COM-FIRE-LIFE-26-000667 Fire · Construction Level 11. Unit numbers: 1101, 1102, 1103, 1104, 1105, 1106, 1107, 1108, 1109, 1110, 1111, 1112, 1113, 1114, 1115, 1116, 1117, 1118, 1119, 1120, 1121. Status: Inspection Phase | Not published | — |
#COM-NEW-26-000369 New · Construction Interior build out of residential units on Level 9. Unit numbers: 0901, 0902, 0903, 0904, 0905, 0906, 0907, 0908, 0909, 0910, 0911, 0912 Status: Inspection Phase | Not published | $3.9M |
#COM-ELC-26-009083 Electrical · Construction Electrical build out of residential units on Level 9. Unit numbers: 0901, 0902, 0903, 0904, 0905, 0906, 0907, 0908, 0909, 0910, 0911, 0912. Status: Inspection Phase | Not published | — |
#COM-MEC-26-004609 Mechanical · Construction Mechanical build out of residential units on Level 9. Unit numbers: 0901, 0902, 0903, 0904, 0905, 0906, 0907, 0908, 0909, 0910, 0911, 0912. Status: Inspection Phase | Not published | — |
#COM-PLM-26-002467 Plumbing · Construction Plumbing build out of residential units on Level 9. Unit numbers: 0901, 0902, 0903, 0904, 0905, 0906, 0907, 0908, 0909, 0910, 0911, 0912. Status: Inspection Phase | Not published | — |
#COM-FIRE-LIFE-26-000583 Fire · Construction Level 9. Unit numbers: 0901, 0902, 0903, 0904, 0905, 0906, 0907, 0908, 0909, 0910, 0911, 0912. Status: Inspection Phase | Not published | — |
#COM-NEW-26-000396 New · Construction Interior build out of residential units on Level 10. Unit numbers: 1001, 1002, 1003, 1004, 1005, 1006, 1007, 1008, 1009, 1010, 1011, 1012 Status: Inspection Phase | Not published | $2.2M |
#COM-MEC-26-004700 Mechanical · Construction Mechanical build out of residential units on Level 10. Unit numbers: 1001, 1002, 1003, 1004, 1005, 1006, 1007, 1008, 1009, 1010, 1011, 1012. Status: Inspection Phase | Not published | — |
#COM-PLM-26-002539 Plumbing · Construction Plumbing build out of residential units on Level 10. Unit numbers: 1001, 1002, 1003, 1004, 1005, 1006, 1007, 1008, 1009, 1010, 1011, 1012. Status: Inspection Phase | Not published | — |
#COM-FIRE-LIFE-26-000647 Fire · Construction Level 10. Unit numbers: 1001, 1002, 1003, 1004, 1005, 1006, 1007, 1008, 1009, 1010, 1011, 1012. Status: Inspection Phase | Not published | — |
#COM-NEW-26-000368 New · Construction Interior build out of residential units on Level 8. Unit numbers: 0801, 0802, 0803, 0804, 0805, 0806, 0807, 0808, 0809, 0810, 0811, 0812 Status: Inspection Phase | Not published | $3.9M |
#COM-FIRE-LIFE-26-000577 Fire · Construction Level 8 Units - 0801, 0802, 0803, 0804, 0805, 0806, 0807, 0808, 0809, 0810, 0811, 0812 Status: Inspection Phase | Not published | — |
#COM-PLM-26-002464 Plumbing · Construction Plumbing build outs for Level 8 Units - 0801, 0802, 0803, 0804, 0805, 0806, 0807, 0808, 0809, 0810, 0811, 0812 Status: Inspection Phase | Not published | — |
#COM-MEC-26-004601 Mechanical · Construction Mechanical Interior build out of residential units Level 8 Units - 0801, 0802, 0803, 0804, 0805, 0806, 0807, 0808, 0809, 0810, 0811, 0812 Status: Inspection Phase | Not published | — |
#COM-ELC-26-009061 Electrical · Construction Electrical build out of residential units 0801, 0802, 0803, 0804, 0805, 0806, 0807, 0808, 0809, 0810, 0811, 0812 Status: Inspection Phase | Not published | — |
#COM-MEC-26-004363 Mechanical · Construction Level 7 Units: 0701, 0702, 0703, 0704, 0705, 0706, 0707, 0708, 0709, 0710, 0711, 0712 Status: Inspection Phase | Not published | — |
#COM-FIRE-LIFE-26-000459 Fire · Construction Level 7 Units: 0701, 0702, 0703, 0704, 0705, 0706, 0707, 0708, 0709, 0710, 0711, 0712 Status: Inspection Phase | Not published | — |
#COM-ELC-26-008593 Electrical · Construction Level 7 Units: 0701, 0702, 0703, 0704, 0705, 0706, 0707, 0708, 0709, 0710, 0711, 0712 Status: Inspection Phase | Not published | — |
#COM-PLM-26-002325 Plumbing · Construction Level 7 Units: 0701, 0702, 0703, 0704, 0705, 0706, 0707, 0708, 0709, 0710, 0711, 0712 Status: Inspection Phase | Not published | — |
#COM-NEW-26-000329 New · Construction Interior build out of residential units on Level 6. Unit numbers: 0601, 0602, 0603, 0604, 0605, 0606, 0607, 0608, 0609, 0610, 0611, 0612. Status: Inspection Phase | Not published | $3.9M |
#COM-FIRE-LIFE-26-000403 Fire · Construction Level 6. Unit numbers: 0601, 0602, 0603, 0604, 0605, 0606, 0607, 0608, 0609, 0610, 0611, 0612. Status: Inspection Phase | Not published | — |
#COM-PLM-26-002269 Plumbing · Construction Plumbing build out of residential units on Level 6. Unit numbers: 0601, 0602, 0603, 0604, 0605, 0606, 0607, 0608, 0609, 0610, 0611, 0612. Status: Inspection Phase | Not published | — |
#COM-MEC-26-004251 Mechanical · Construction Mechanical build out of residential units on Level 6. Unit numbers: 0601, 0602, 0603, 0604, 0605, 0606, 0607, 0608, 0609, 0610, 0611, 0612. Status: Inspection Phase | Not published | — |
#COM-ELC-26-008385 Electrical · Construction Electrical build out of residential units on Level 6. Unit numbers: 0601, 0602, 0603, 0604, 0605, 0606, 0607, 0608, 0609, 0610, 0611, 0612. Status: Inspection Phase | Not published | — |
#COM-ELC-26-006345 Electrical · Construction Pulled fiber and cat6 from telco location to each unit. Pulled cat6 in each unit at living room loation. Status: Inspection Phase | Not published | — |
#COM-MEC-26-002371 Mechanical · Construction Mechanical build out of residential units on Level 5. Unit numbers: 0501, 0502, 0503, 0504, 0505, 0506, 0507, 0508, 0509, 0510, 0511, 0512. Status: Inspection Phase | Not published | — |
#COM-PLM-26-001450 Plumbing · Construction Plumbing build out of residential units on Level 5. Unit numbers: 0501, 0502, 0503, 0504, 0505, 0506, 0507, 0508, 0509, 0510, 0511, 0512. Status: Inspection Phase | Not published | — |
#COM-ELC-26-004991 Electrical · Construction Electrical build out of residential units on Level 5. Unit numbers: 0501, 0502, 0503, 0504, 0505, 0506, 0507, 0508, 0509, 0510, 0511, 0512. Status: Inspection Phase | Not published | — |
#COM-NEW-26-000193 New · Construction Interior build out of residential units on Level 5. Unit numbers: 0501, 0502, 0503, 0504, 0505, 0506, 0507, 0508, 0509, 0510, 0511, 0512. Status: Inspection Phase | Not published | $3.9M |
#COM-MEC-26-000242 Mechanical · Construction S/C of South Tryon T2 Status: Inspection Phase | Not published | — |
#COM-ELC-26-000482 Electrical · Construction All new electrical installation (i.e. power distribution, fire alarm, low voltage) for a 42 story mixed-use office and residential tower and associated portion of a 10 story parking podium. Status: Inspection Phase | Not published | — |
#COM-PLM-26-000145 Plumbing · Construction S/C of South Tryon T2 Status: Inspection Phase | Not published | — |
#COM-SHL-26-000004 Shell · Construction Permit for the core and shell of a 42 story mixed-use office and residential tower and associated portion of a 10 story parking podium Status: Inspection Phase | Not published | — |